11.6 INSPECTION OF CONDENSATE DRAIN ASSEMBLY
Inspect the condensate drain assembly as follow.
Inspecting the Condensate Drain assembly
1. Inspect and ensure the Condensate Drain Assembly is properly installed as shown in
Figure 6-1 of Chapter 6.
2. Remove the plug from the Condensate Drain Assembly and fill with fresh water.
WARNING!
The condensate drain assembly must be filled with water when the
Esteem boiler is in operation. The condensate drain assembly
prevents flue gas emissions from entering the condensate line.
Failure to ensure trap is filled with water could result in severe
personal injury or death.
3. Re-Install the plug into the condensate drain assembly.