If the IEC61850-9-2LE communication is interrupted during current
injection, the report tool in PCM600 will display the current that was
injected before the interruption.
IEC10000032-1-en.vsd
IEC10000032 V1 EN
Figure 11:
PCM600 report tool display after communication interruption
9.7
Testing the protection functionality
Each protection function must be tested individually by secondary injection.
•
Verify operating levels (trip) and timers.
•
Verify alarm and blocking signals.
•
Use the disturbance handling tool in PCM600 to evaluate that the protection
function has received the correct data and responded correctly (signaling and
timing).
•
Use the event viewer tool in PCM600 to check that only expected events have
occurred.
Section 9
1MRK 511 360-UEN A
Testing IED operation
74