7.
Manually execute Raise commands to step up the tap changer one step for all
transformers in the parallel group
8.
Check that the value of
BUSVOLT
is below overvoltage blocking level
OVPartBK
and above the undervoltage blocking level
UVPartBK
.
9.
Set the control mode to
Auto
for each transformer in the parallel control group
The Master in the parallel group will issue a Lower command after time delay t1,
which will also be repeated by the Follower transformers in the group.
10. Set Transformer 2 to Master of the parallel group and T1 to Follower (in that
order) and repeat steps 7 to 10. Undertake this same test by setting each
Transformer in turn to Master
11. Note that voltage regulation will be mutually blocked if no transformer is set to
Master in the parallel group. To confirm this function, set T1 as Master and the
other transformers in the parallel grouper set as Follower. Without allocating a
new Master, set T1 to Follower and note the
Automatic
block state on the local
HMI for all parallel transformers
12. Restore T1 to Master of the parallel transformer group and ensure that control
mode for each transformer is
Automatic
.
11.1.5
Completing the test
After the test is completed and relevant disturbance records are saved to document the
test, go to
Main menu/Clear
on the local HMI and clear all LEDs, the process
eventlist and disturbances from the IED.
Section 11
1MRK 511 360-UEN A
Primary injection testing
196
Bay control REC670 2.1 IEC
Commissioning manual