1.
Inject current 20% bigger than the set overcurrent pickup level under setting
parameter
IOC>
(for example, 1.2 · 1.35 · 0.587A = 0951A at 50Hz for this
SCB) in phase L1 only.
2.
Check that function binary output signals STOCL1 and STOC are set to one.
3.
Check that function binary output signals TROC and TRIP are set to one after the
set time under parameter
tOC
(that is, 30s for this SCB) has expired.
4.
If any of these signals are used for tripping, signaling and/or local/remote
indication check that all relevant contacts and LEDs have operated and that all
relevant GOOSE messages have been sent.
5.
Check that service value from the function for current in phase L1, on the local
HMI under
Main menu/Test
is approximately 476A (that is, 0.951A · (500/1)
= 476A).
6.
Stop injection of all currents (that is, set all currents back to 0A).
7.
Check that all above mentioned function binary output signals now have logical
value zero.
8.
Repeat above steps 1-7 for phase L2 and phase L3.
Note that the operation of this feature is based on current peak value.
That means that this overcurrent function is also able to operate for the
same current magnitude but for different injected frequencies. If
required repeat this injection procedure for example for the 3rd
harmonic by just simply injecting 3 · 50 = 150Hz currents with the
same magnitude. Obtain results shall be the same.
Undercurrent feature
1.
Inject SCB rated current (that is, 0.587A at 50Hz for this SCB) in all three
phases.
2.
Lower phase L1 current 10% under the set value for setting parameter
IUC<
(that is, 0.9 · 0.7 · 0.587A = 0.370A at 50Hz for this SCB).
3.
Check that function binary output signals STUCL1 and STUC are set to one.
4.
Check that function binary output signals TRUC and TRIP are set to one after the
set time under parameter
tUC
(for example, 5s for this SCB) has expired.
5.
If any of these signals are used for tripping, signaling and/or local/remote
indication check that all relevant contacts and LEDs have operated and that all
relevant GOOSE messages have been sent.
6.
Check that service value from the function for current in phase L1, on the local
HMI under
Main menu/Test
is approximately 185A (that is, 0.370A · (500/1)
= 185A).
7.
Stop injection of all currents (that is, set all currents back to 0A).
8.
Check that all above mentioned function binary output signals now have logical
value zero because they will be automatically blocked by operation of built-in
reconnection inhibit feature.
9.
Repeat above steps 1-8 for phase L2 and phase L3.