5 . . .Installation
Sensor
G12029
3 S2 E2 E1 S1 M1M2
M 20 mm /
1/2"
NPT
PA
2
1
FE
Terminals for signal cable
Terminal for potential equalization
1
2
Figure 37 Connection to sensor in remote mount design (example)
Note
If the O-ring gasket is seated incorrectly or damaged, this
may have an adverse effect on the housing protection class .
Follow the instructions in chapter "Opening and closing the
terminal box" on page 14 to open and close the housing
safely.
Observe the following points:
• Lead the signal cable into the housing as shown.
• Connect the cables in accordance with the electrical
connection diagram. If present, connect the cable
shielding to the earthing clamp provided.
• Use wire end ferrules when connecting.
• Close unused cable entries using suitable plugs.