Connection, installation / mounting
System Manual
│36
5.2.2
Mounting in clinker facades
For mounting the installation boxes in clinker facades, perform the following points:
Fig. 12: Mounting installation boxes in clinker facades
1. Chisel a hole according to the size of the outdoor station used into the facade provided.
– The suitable template is enclosed with the flush-mounted installation box.
– Dimensional drawings, see chapter 5.9.4 “Installation boxes - flush-mounted installation“
on page 59.
– The installation depth of the flush-mounted installation box is 46 mm.
2. Insert the flush-mounted installation box.
– Attention:
Ensure that the encircling "Collar" of the flush-mounted installation box rests on the
facade. The encircling "Collar" of the flush-mounted installation box must not be
submerged in the facade. The device can then not be mounted later.
– Fix the flush-mounted installation box into the cut-out of the facade with the aid of the
elongated holes.
– The hollow spaces between the flush-mounted installation box and the clinkers can be
filled with PU foam.
– For this, break out the holes in the corners of the box angled at 45°.
– Insert the extension tube of the PU foam and fill the cavities.
– Use a low-expansion foam to prevent foam from penetrating the flush-mounted box.
If necessary, use foam cleanser to remove the contaminations.
– No additional accessories are necessary for mounting.
3. Mounting the outdoor station.
– see chapter 5.3 “Outdoor stations“ on page 39.