B
Checklist installation
Checklist
Run.
No.
Requirement
fulfilled
Notes
2
Installation
yes
no
2.1
Is it guaranteed that the safety switch devices are not
short-circuited due to a wiring fault?
2.2
Is it guaranteed that the safety switch devices are not
short-circuited due to a wiring fault?
3.3
Was the wiring checked by means of the installation
plan?
2.4
Are all the plugs labelled according to their allocation?
2.5
Are the connecting terminals with screws applied with
the specified breakaway torque?
2.6
Is guaranteed that the isolation of the lines does not
lead to a faulty contact?
2.7
Was the reliability of all the clamp connections con-
trolled by a mechanical tensile load?
2.8
Was a visual inspection of the installed components
accomplished?
2.9
Were necessary installation distances kept to other
components?
2.10
Do the components fulfill the environmental conditions
of the application?
2.11
Does the system fulfill the necessary degree of protec-
tion?
2.12
Is degree of pollution 2 kept?
2.13
Is the system protected against aggressive media?
Date:.........................Name: ...................................Sign: ......................................................
VIPA System SLIO
Checklist installation
HB300 | SM-S | 02x-1SD10 | en | 20-02
131