Attaching the hardware to racks
StockSAVER manual - Software version 2.1
38
5.
As an alternative to manual input, rack Location assignments can be imported via CSV.
See
Importing Location assignments from CSV
6.
Click Check to check the configuration for errors.
7.
Save the rack configuration, click OK and close the dialog.
5.8.6
Configuring the bus cabling
Using Bus cabling configuration, replicate the physical bus cabling in the software as
sketched on the template in the installation instructions.
1.
Add all racks connected to the SmartBox bus: Click Add rack.
2.
Select the rack from the Add rack dialog.
3.
Click the SmartBox icon to draw the bus wiring between the SensorBoxes.
4.
Click Check to check the configuration for errors.
5.
Save the bus wiring, click OK and close the dialog.