SYSTEM STARTUP
Setting the Address
Set the address DIP switches on each module to a unique address between 1 and 15.
CIE Serial Bus Termination
Remove the jumper LK1 from each module unless the module is the last device on the CIE serial bus.
Testing the Installation
Once all field wiring connections are complete, test the power supply, field circuits, and panel GUI to ensure
proper operation of the XT+. Apply AC Power and allow the XT+ to boot. The following messages will appear
on the LCD(s):
V1g60 Module
Initializing...
Once the initialization process is complete, the LCD will display the following when in normal standby mode:
MAN&AUTO
Testing the Power Supply
Perform the following tests to confirm operation of the power supply:
1. Apply AC and battery power to the XT+.
2. Check that the AC Normal LED is illuminated on the power supply.
System Startup
VES Fire Detection Systems
XT+ Releasing Control Unit Installation Manual
Version 1.00 | December 2018 | MAN-1252VES
Page 35