26 Chapter 3 Installation
SmartCabinet Series Solution Product for IDC or Computer Rooms User Manual
Figure 3-18 Remove the perforated board at the air outlet
2. Push the air channel parts into the top frame body from top to bottom and use M6X16 screws (4 PCS) to fix the
parts on the top frame body as shown in Figure 3-19.
Figure 3-19 Installing air channel parts
After installing the air duct parts, the customer needs install the air duct and the connection between the air duct and
the cabinet is shown in Figure 3-20.
Figure 3-20 Installation of air duct
Note
1. Air duct center is 1824mm away from the bottom plate of the unit;
2. Air duct size is 300 × 400mm, and fixing holes for connecting to the air flow guiding pipe are reserved on the air duct; the
connection between the air duct and air flow guiding pipe needs to be fixed during field construction;
3. The system can be equipped with an induced draft fan, installed in the air duct outlet to reduce the air duct resistance and
ensure that the unit performs normal cooling operation;
4
.
The longest air duct supported by the system is 10m long with two elbow bends, and contact Vertiv service department if the
length exceeds 10m.
Hook
installation hole