3
Fold the template along the yellow dotted lines to match the rack holes exactly.
4
Record the rack positions to help you locate them easily when mounting the
hardware.
5
Next, assess the SAS cables to be sure that you have the correct lengths for
your installation.
The following procedure provides information to help you verify that you have the
correct lengths of SAS cable.
To determine SAS cable requirements
1
Note that each rack unit (RU) is 44.50 mm (1.752 inches) in height. The
NetBackup 5240 Appliance and the NetBackup 5240 Storage Shelf are both
2RU high.
2
SAS cables are 1 meter (3.28 feet) or 3 meter (9.84 feet) long. The 1-meter
cable is long enough to connect an appliance to the fourth storage shelf,
assuming that the recommended configuration is used.
Verify that your cables are long enough to connect all of the devices.
3
Order the 3m cable if the 1m cable is not long enough.
Installing the storage shelf rails
Best practices recommend that the storage shelves are installed lower in the rack
than the appliance.
Adding one or more storage shelves to an operating 4TB appliance that does not have any storage shelves
Installing the storage shelf rails
88
Содержание NetBackup 5240
Страница 1: ...NetBackup Appliance Hardware Installation Guide Release 2 7 3 NetBackup 5240 Document Revision 1 ...
Страница 4: ......
Страница 22: ...Preinstallation requirements Prerequisites for IPMI configuration 22 ...
Страница 42: ...Installation procedures Connecting a 4TB appliance to more than one storage shelf 42 ...
Страница 43: ...43 Installation procedures Connecting a 4TB appliance to more than one storage shelf ...
Страница 66: ...Installation procedures Accessing and using the Veritas Remote Management interface 66 ...
Страница 140: ...Adding storage shelves to an operating 4TB appliance that has at least one storage shelf attached Recabling 140 ...