12
Be sure that the blue clips on the connectors in both ports point up.
13
Connect a SAS-3 cable to port B of the bottom I/O module in the second shelf.
Connect the other end of the cable to port A on the bottom I/O module in the
first shelf.
Next, connect network and power cables. Turn on the storage shelves and the
appliance per the required sequence. Verify that all units are functioning correctly.
Connecting four storage shelves to an appliance
Note:
The cables in the following diagrams are shown in different colors for
demonstration purposes only. The actual cables are black.
107
Adding one or more storage shelves to an operating 4TB appliance that does not have any storage shelves
Connecting four storage shelves to an appliance
Содержание NetBackup 5240
Страница 1: ...NetBackup Appliance Hardware Installation Guide Release 2 7 3 NetBackup 5240 Document Revision 1 ...
Страница 4: ......
Страница 22: ...Preinstallation requirements Prerequisites for IPMI configuration 22 ...
Страница 42: ...Installation procedures Connecting a 4TB appliance to more than one storage shelf 42 ...
Страница 43: ...43 Installation procedures Connecting a 4TB appliance to more than one storage shelf ...
Страница 66: ...Installation procedures Accessing and using the Veritas Remote Management interface 66 ...
Страница 140: ...Adding storage shelves to an operating 4TB appliance that has at least one storage shelf attached Recabling 140 ...