Revision F August 2022
2)
Anchor the Tension Strut Backup (Figure 17)
Locate Tension Strut Backup and Monorail on foundation with side of Monorail on the
construction line (p. 24).
Verify that any applicable Transition Panels fit properly before
anchoring Backup.
Drill
7/8” [22 mm]
diameter by 5 3/4” [145 mm] anchor boreholes in
foundation using the Backup as template. Anchor the Backup to the concrete foundation
using an approved adhesive supplied with the QuadGuard
®
M10 (p. 16).
Note:
Verify that any applicable Transition Panels fit properly before anchoring Backup.
Caution:
Every hole in the Backup and Monorail must be anchored by a stud
using an approved adhesive (p. 16).
3)
Anchor the Monorail
Monorail Placement for Tension Strut Backup (Figure 21)
Locate Monorail on foundation with side of Monorail on the construction line and rear edge
of Backup foot 4” forward of edge of foundation.
Orient the Monorail so that the Monorail tongues face the
Backup.
Warning:
Improper alignment at the Monorail splice joints may prevent proper
system collapse during an impact (p. 24, Detail 19a).
It is important to align each segment of Monorail from the back to the front of the system
(±1/4” [6 mm]). Anchor each Monorail section using the Valtir approved adhesive kits
provided (p. 16).
Figure 17
Anchoring Tension Strut
Backup to Foundation
TENSION STRUT BACKUP
APPROVED ADHESIVE
WITH 3/4 X 7 ANCHOR ASSEMBLY
Содержание QuadGuard M10
Страница 1: ......
Страница 41: ...Valtir com 40 Revision F August 2022 QuadGuard M10 w Tension Strut Backup QGMTSCVR U...
Страница 42: ...Valtir com 41 Revision F August 2022 TS Concrete Pad 618686...
Страница 43: ...Valtir com 42 Revision F August 2022 TS Concrete Pad 8 w Rebar 618686...
Страница 44: ...Valtir com 43 Revision F August 2022 TS Concrete Pad 8 wo Rebar 618686...
Страница 45: ...Valtir com 44 Revision F August 2022 Tension Strut Backup 627448...
Страница 46: ...Valtir com 45 Revision F August 2022 Monorail Assembly 625637...
Страница 47: ...Valtir com 46 Revision F August 2022 Diaphragm Assembly 625650...
Страница 48: ...Valtir com 47 Revision F August 2022 Shim Kit 627518...
Страница 49: ...Valtir com 48 Revision F August 2022 Fender Panel Assembly 608236...
Страница 50: ...Valtir com 49 Revision F August 2022 Nose Assembly 626814...
Страница 51: ...Valtir com 50 Revision F August 2022 31 W Beam Guardrail Transition QGMTSCVR TWLR...
Страница 52: ...Valtir com 51 Revision F August 2022 Thrie Beam Guardrail Transition QGMTSCVR TTLR...
Страница 53: ...Valtir com 52 Revision F August 2022 Safety Shape Barrier Transition QGMTSCVR T4...
Страница 54: ...Valtir com 53 Revision F August 2022 Single Slope Transition QGMTSCVR T6...
Страница 55: ...Valtir com 54 Revision F August 2022 Vertical Barrier Transition QGMTSCVR ES...
Страница 56: ...Valtir com 55 Revision F August 2022 Vertical Barrier Transition Extended QGMTSCVR SPE...
Страница 57: ...Valtir com 56 Revision F August 2022 NOTES...
Страница 58: ...Valtir com 57 Revision F August 2022 NOTES...
Страница 59: ...Valtir com 58 Revision F August 2022 NOTES...
Страница 60: ......