ULB PROPRIETARY RIGHTS NOTICE
- This document contains the confidential and proprietary information of ULB. You may not possess,
use, copy or disclose this document or any information in it for any purpose without express written permission. Neither receipt from any source,
nor possession of this document, constitutes such permission. Possession, use, copying or disclosure by anyone without express written
permission of ULB is not authorized and may result in criminal and/or civil liability.
U:\ILB\5_Technical Manual\TLB-R1000-480-OS_NO ALL\TLB-R1000_480_MANUAL_Rev03.docx
Page
22
of
35
Powering up Master – Slave Load banks
Note: For master to identify all salves load banks, master load bank should be powered up
last (i.e. power up all slave load banks first) or all load banks in the network should be
powered up simultaneously.
If steps of physical connection, settings and powered up are done correctly then following
screen should be displayed on Master load bank (See Fig.8)
Fig.8 Multiple Load bank Operation
Click <MULTIPLE> to operate load banks in Master – Slave mode. Following screen showing
ID, KW capacity, Fault and communication status of each load bank will show on master load
bank (See Fig.9)
Note: Click <SINGLE> button will allow individual load bank operation with an option to
operate in multiple load bank mode any time.