Commissioning
Please make the under procedures checking before commissioning,
1. Ensure all the connections are correct and wires diameter is suitable.
2. Ensure that the controller DC power has fuse, controller‘s positive and negative connected to
start battery are correct.
3. Take proper action to prevent engine to crank disconnect (e. g. Remove the connection wire
of fuel valve). If checking is OK, make the start battery power on; choose manual mode and
controller will executive routine.
4. Set controller under manual mode, press “start” button, genset will start. After the setting
times as setting, controller will send signal of Start Fail; then press “stop” to reset controller.
5. Recover the action of stop engine start (e. g. Connect wire of fuel valve), press start button
again, genset will start. If everything goes well, genset will normal run after idle running (if idle
run be set). During this time, please watch for engine’s running situations and AC generator’s
voltage and frequency. If abnormal, stop genset running and check all wires connection
according to this manual.
6. Select the AUTO mode from controller’s panel, connect remote start signal. genset will be
started automatically and into normal running, then controller send signal to close generator.
7. Cut-off remote start signal, the genset will be stopped automatically and the Open Generator
signal will be send out. If not like this, please check ATS’ wires connection of control part
according to this manual.
8. If there is any other question, please contact Smartgen’s service.
24