48
RTAF-SVX001A-EN
Pre-Start
Upon completion of installation, complete the Sintesis™
RTAF Installation Completion Check Sheet and Request for
Trane Service checklist in chapter
“Log and Check Sheets,”
p. 86
.
Important:
Start-up must be performed byTrane or an
agent of Trane specifically authorized to
perform start-up and warranty of Trane
products. Contractor shall provideTrane (or
an agent ofTrane specifically authorized to
perform start-up) with notice of the
scheduled start-up at least two weeks prior
to the scheduled start-up.