Pre-Installation
12
RTAF-SVX001A-EN
Installation Requirements
A list of the contractor responsibilities typically associated
with the unit installation process is provided in
Table 2
.
Table 2.
Installation requirements
Type
Trane Supplied
Trane Installed
Trane Supplied
Field Installed
Field Supplied
Field Installed
Foundation
• Meet foundation requirements
Rigging
• Safety chains
• Clevis connectors
• Lifting beam
• Spreader bar
Isolation
• Elastomeric isolators
(optional)
• Elastomeric isolators (optional)
Electrical
• Circuit breakers
(optional)
• Unit mounted starter
• Circuit breakers (optional)
• Electrical connections to unit mounted starter
• Wiring sizes per submittal and NEC
• Terminal lugs
• Ground connection(s)
• BAS wiring (optional)
• Control voltage wiring
• Chilled water pump contactor and wiring
• Option relays and wiring
Water piping
• Flow switch
• Taps for thermometers and gauges
• Thermometers
• Water flow pressure gauges
• Isolation and balancing valves in water piping
• Vents and drain
• Waterside pressure relief valves
• Water strainer
Insulation
• Insulation • Insulation
Water Piping Connection Components
• Grooved pipe
• Flange kit (optional)
Other Materials
• R-134a or R-513A
refrigerant
• Dry nitrogen
(optional)
“Sintesis Model RTAF Installation
Completion Check Sheet and Request
for Trane Service”
(RTAF-ADF001*-EN,
see
“Log and Check Sheets,” p. 86
)
Chiller Start-up Commissioning
(a)
• Trane, or an agent of
Trane specifically
authorized to perform
start-up of Trane
®
products
(a) Start-up must be performed by Trane or an agent of Trane specifically authorized to perform start-up and warranty of Trane
®
products. Contractor shall
provide Trane (or an agent of Trane specifically authorized to perform start-up) with notice of the scheduled start-up at least two weeks prior to the scheduled
start-up.