5.4.6
Equipment Boom Cable Kit (Brand) (EQB)
Cabling
All cabinets within the boom must be pulled by Hospital/Contractor if not already
pulled by boom manufacturer
Conduit
Terminated within 18" of the center of the ceiling mount
Power
Per boom manufacturer specifications
Plumbing
Per boom manufacturer specifications
Access Panel
One (1) 24" x 24" access panel adjacent to suspension
Structural
Per boom manufacturer specifications
ITEM-ITEM
QTY
SIZE
EQB – A
2
2"
5.4.7
Anesthesia Boom Cable Kit (Brand) (ANB)
Cabling
All cables within the boom must be pulled by Hospital/Contractor if not already
pulled by boom manufacturer
Conduit
Terminated within 18" of the center of the ceiling mount
Power
Per boom manufacturer specifications
Plumbing
Per boom manufacturer specifications
Access Panel One (1) 24" x 24" access panel adjacent to suspension
Structural
Per boom manufacturer specifications
ITEM-ITEM
QTY
SIZE
ANB – A
1
2"
5.4.8
Navigation Arm (NAM)
Conduit
Terminated to 10" x 10" x 4" NEMA type 1 box within 18" of the center of the ceiling
mount.
Power
No additional power required.
Access Panel
One (1) 24" x 24" access panel adjacent to suspension
Structural
• Optimal location for center of Navigation camera is 47" above finished floor.
• Stryker preinstall plate is installed per customer structural engineer specs at 4"
above finished ceiling.
• A 21" circular hole centered on Stryker preinstall plate in the finished ceiling is
required for installation. A 24" diameter ceiling cover conceals hole after suspen-
sion is installed.
• The Contractor/electrician to hardwire Stryker electrical whip during Stryker
installation.
• Load location: X=31", Y=45"
• Maximum deflection: 1 degree
ITEM-ITEM
QTY
SIZE
NAM – A
1
2"