ORIS equipment must be fully assembled and connected to phone, data and power.
10. The proper Stryker cable kits must be pulled through any non-Stryker ceiling-mounted equip-
ment prior to the Stryker installation date.
-
International Only:
If Stryker technicians are requested to pull cables through non-Stryker
ceiling-mounted equipment, the vendor of the equipment must be present to assist and pro-
vide instructions. The vendor will maintain responsibility for the finished, combined product.
11. All rooms must be reserved for Stryker Installation technicians only at all times during the
installation dates.
4.3 Stryker Responsibilities
1. Provide design assistance and recommendations.
2. Provide rough-in, cabling, electrical, and voice/data requirements listed in this manual.
3. Provide rough-in drawings.
4. Provide the hospital with a scope of work for Stryker's equipment installation.
5. Inventory all Stryker ORIS System components.
6. Pull all cables within the operating room. Hospital provides and pulls all cables outside of the
operating room, including auditoriums and conference rooms.
7. Terminate and test all low voltage cabling used to connect ORIS equipment with actual equip-
ment or functionally equivalent signal generators.
8. Break down packaging material and gather all trash in a central location in the work area for
Hospital/Contractor removal.
9. Perform a final review and "walk through" of the installation to ensure all equipment is func-
tioning and all installation requirements have been met.