Tests
Test 99: Update to New Boiler Water Level Sensor (Update Kit Part # 10344)
1
2
3
4
5
6
7
8
9
1. Remove the old boiler water level sensor.
2. Install the new boiler water level sensor using the adapter flange, gasket and bolts.
3. Connect the red wire to the red wire and the black wire to the black wire. Put a wire nut cap on the
yellow wire.
4. How to release wires from spring type terminal strips (use in steps 6, 7, 9, 10).
5. In
Panel 2 locate the first blue terminal strip section on TS1.
6. Release the red and black wires shown.
7. In
Panel 2 locate the first white terminal strip section on TS1.
8. Release the 8th purple and red wires and tuck them into the panduit cable hider (they will no longer
be used).
9. Put the red wire from step 6 into the top open hole created in step 8; Also, put the black wire from
step 6 into the lower open hole created in step 8.
10. Remove the old boiler water level sensor signal conditioner on Panel 3.
10