Speck pumpen VZ 11 B Series Скачать руководство пользователя страница 24

 
OPERATING INSTRUCTIONS 

 

 

 

 

24 

Commissioning  

Decommissioning 

6.1 

Preparing for operation 

For commissioning fill the pump with operating 

liquid  up  to  middle  of  shaft.  This  may  be  ef-

fected through suction, discharge or operating 

liquid pipe. 

CAUTION

 

Dry run of the pump shall be avoided by all 

means.  Otherwise  any  warranty  for  any 

consequences  resulting  including  claims 

for compensation of damages invalidate. 
Check  the  direction  of  rotation.  Wrong 

direction  of  rotation  leads  to  damages  at 

the pump. 

6.2 

Commissioning 

• 

Switch-on  motor,  open  shut-off  valve  V

F

 

resp. V

K

.  

• 

When  starting  operation  with  closed  suc-

tion  side,  open  the  ventilation  device  be-

fore  and  close  it  after  having  reached the 

operating speed. 

6.3 

Adjustment of flow volume 

6.3.1  Open  circulation  cooling  according 

to illustr. 3a 

Open  shut-off  valve  V

F

 

while  the  pump  is 

running and adjust regulating valve r

F

that the 

pressure  at  mano-vacuum  meter  m

B

  is  ca.  0 

bar (max. 0,2 bar). Lock the regulating valve r

F

 

in  this  position.  Maximum  temperature  of 

operating liquid see 3. Then the vacuum pump 

draws the quantity of clean water as indicated 

in diagram 1

6.3.2  Closed  circulation  cooling  accord-

ing to illustr. 4a 

While the vacuum pump is running adjust the 
regulating valve r

F

, 

that the pressure at mano-

vacuum meter m

B

 is differing no more than +/- 

0,2 bar from compression pressure. The flux of 

cooling  liquid  K  will  be  adjusted  through  the 
regulating valve r

K

 

at open shut-off device. The 

regulating valves are to be locked. 
In order to control the liquid level N there may 

be mounted a valve at the connection U

e3

. An 

automatic  draining  valve  at  this  connection 

controles  and  regulates  the  liquid  level  auto-

matically. 

6.3.3  Continuous  cooling  according  to 

illustr. 5a 

Open  shut-off  valve  V

F

 

while  the  pump  is 

running and adjust regulating valve r

F

that the 

pressure  at  mano-vacuum  meter  m

B

  is  ca.  0 

bar  (max.  0,2  bar).  Then  the  vacuum  pump 

draws the quantity of clean water, as indiated 

in diagram 1. 

6.3.4  For automatic systems according to 

illustr. 3c 

The  required  temperature  of  operating  liquid 

has to be adjusted at the thermostatic regulat-
ing  valve  r

F2

.

The  pressure  reducing  regulator 

r

F3

 

will be adjusted that the pressure at mano-

vacuum meter m

B

 will not exceed considerably 

0 bar. 

6.4 

Decommissioning 

Close  shut-off  device  V

F

  resp.  V

K

,  switch-off 

motor, possibly open ventilation device h

 

If  the  decommissioning  is  made  to  effect 

any  works  at  the  pump,  the  drive  must  be 

secured so that it cannot be switched on. 
When using the pump for hazardous gases, it 

has to be rinsed thoroughly before opening. In 

order to prevent that easily inflammable gases 

will  cause  an  explosive  air/gas  mixture,  the 

pump has to be rinsed sufficiently with inertgas 

before opening it and before restarting it after 

opening. 
In case of danger of frost or danger of congeal-

ing of the ring liquid, pump and liquid separator 

have to be emptied by withdrawing all plugs at 

bottom.  This  is  also  applicable  for  a  longer 

shut-down period. 

Operation 

7.1 

General 

When  delivering  air  and  other  inert  gases 

normally water is used as ring liquid. Other ring 

liquids than water may also be used in order to 

meet  with  the  requirements  to  the  kinds  of 

gases  and  separators  chosen.  The  ring  liquid 

has  to  be  free  from  foreign  bodies,  as  other-

wise the casing will be worne out. Use appro-

Содержание VZ 11 B Series

Страница 1: ...H CO KG zertifiziert DIN EN ISO 9001 Betriebsanleitung Operating Instructions Mode d emploi Fl ssigkeitsring Vakuumpumpen Liquid Ring Vacuum Pumps Pompes vide anneau liquide VZ 110B VZ 180B VZ 110G VZ...

Страница 2: ...nzip 5 5 Aufstellung Einbau 5 5 1 Aufstellungsort 5 5 2 Einbau 5 5 3 Leitungen 6 5 3 1 Saugleitung 6 5 3 2 Druckleitung 6 5 4 Elektrischer Anschluss 6 5 5 Betriebsarten 7 5 5 1 Offene Umlaufk hlung 7...

Страница 3: ...lnbetriebnahme vom Monteur sowie dem zust ndigen Fachpersonal Betrei ber zu lesen und muss st ndig am Einsatzort der Pumpe Anlage verf gbar sein Es sind nicht nur die unter diesem Hauptpunkt Si cherh...

Страница 4: ...siehe z B Vorschriften des VDE und der rtlichen Energieversorgungsunter nehmen 2 6 Sicherheitshinweise f r War tungs Inspektions und Monta gearbeiten Der Betreiber hat daf r zu sorgen dass alle Wartu...

Страница 5: ...ne pulsation sarme Verdichtung Eine kontinuierliche Zuf hrung bzw K hlung der Betriebsfl ssigkeit im Normalfall Wasser ist erforderlich Sie f hrt die entstehende Ver dichtungsw rme ab und erg nzt die...

Страница 6: ...me zu pr fen 5 3 1 Saugleitung In der Saugleitung sollte ein R ckschlagventil eingebaut werden um das F llen der Vakuum leitung mit der Ringfl ssigkeit bzw um Druck abfall im Vakuum System zu vermeide...

Страница 7: ...it kein Wert gelegt wird Der Aufbau erfolgt nach Abb 5a Der An schluss UU wird verschlossen Die Betriebs fl ssigkeit B besteht aus Frischfl ssigkeit F Der erforderliche Frischfl ssigkeitsdruck soll 0...

Страница 8: ...turf hler zu rF2 UA Fl ssigkeitsablauf UB Anschluss f r Betriebsfl ssigkeit UN Anschluss f r Kontrollventil US Saugleitungsanschluss DU Druckleitungsanschluss UU Anschluss f r Umlauffl ssigkeit Ue Ent...

Страница 9: ...BETRIEBSANLEITUNG 9 Durchlaufk hlung Abb 4a nebenst Fl ssikeitsabscheider Abb 4b Fl ssigkeits Aufbauabscheider Beh lter mit Schwimmerventil Abb 4c nebenst Fl ssigkeitsabscheider...

Страница 10: ...BETRIEBSANLEITUNG 10 Geschlossene Umlauflaufk hlung Abb 5a nebenstehender Fl ssigkeitsabscheider Abb 5b Fl ssigkeits Aufbauabscheider Abb 6 Lage des Betriebswasseranschlusses...

Страница 11: ...s ue3 ein Ventil angeschlossen werden Ein automatisches Entleerungsventil an diesem Anschluss kontrolliert und reguliert den Fl ssigkeitsstand selbstt tig 6 3 3 Durchlaufk hlung nach Abb 4 Bei laufend...

Страница 12: ...eingestellt werden dass das gew nschte Saugverm gen bzw der gew nschte Volu menstrom erreicht jedoch Kavitation verhin dert wird Das Regulierventil ist in dieser Ein stellung zu blockieren Bei Vakuumb...

Страница 13: ...d ebenso des Saugverm gens eintritt siehe 7 2 Temperatur der Fl ssigkeit durch geeig nete Ma nahmen senken Gas bzw Fl ssigkeitskan le verschlossen Pumpe zerlegen und besonders die Kan le reinigen Glei...

Страница 14: ...2200 Gaseintrittstemperatur trocken 160 C wasserdampfges ttigt 80 C VZ 110 180 Drehzahl min 1 50Hz 60 Hz 1450 1750 Betriebsfl ssigkeit Temperatur 10 C 60 C Dichte 1200 kg m3 Viskosit t 4 mm2 s berdruc...

Страница 15: ...stallation 18 5 2 Installation 18 5 3 Pipes 19 5 3 1 Suction pipes 19 5 3 2 Discharge Pipes 19 5 4 Electrical connection 19 5 5 Operation modes 19 5 5 1 Open circulation cooling 19 5 5 2 Closed circul...

Страница 16: ...mp s place of opera tion at all times You should not just consider the general safety information listed in this point specific safety information is also con tained in the other main points 2 1 Marki...

Страница 17: ...ts who are adequately informed having thor oughly read these operating instructions Basically the pump must have stopped before carrying out any work on it The procedures described in the operating in...

Страница 18: ...Installation CAUTION The non observation of all safety informa tions given under 5 Setting up Installation shall invalidate any claims of warranty including claims for compensa tion of damages 5 1 Pla...

Страница 19: ...faultless electrical installation required taking into account appropriate guide lines and VDE regulations serious consideration is necessary of the pump s direction of rotation flow direction which i...

Страница 20: ...p will be provided with a gas ejector pump 5 6 Setting up of the unit A side mounted liquid separator has to be installed thus that the liquid discharge is at the same level as the shaft The liquid se...

Страница 21: ...PERATING INSTRUCTIONS 21 Setting up schema Open circulating cooling illustr 3a side mounted separator illustr 3b top mounted separator Illustr 3c thermostatically controlled process liquid temperature...

Страница 22: ...OPERATING INSTRUCTIONS 22 Continuous cooling Illustr 4a side mounted separator Illustr 4b top mounted separator Tank with float valve fitted Illustr 5a side mounted separator...

Страница 23: ...OPERATING INSTRUCTIONS 23 Closed circulation cooling Illustr 5a side mounted separator Illustr 4b top mounted separator Illustr 6 position of service liquid connection...

Страница 24: ...e connection Ue3 An automatic draining valve at this connection controles and regulates the liquid level auto matically 6 3 3 Continuous cooling according to illustr 5a Open shut off valve VF while th...

Страница 25: ...ty resp a reduced volume flow however gives the possibility of safing fresh water resp cooling liquid at open resp closed circulation cooling Such liquid quantity should be regulated by the regulating...

Страница 26: ...ozzle IG elevated by 300 mm or through a connecting pipe with nozzle to the liquid separator a The use of a gas ejector also avoids cavitation If a large amount of dirt is deposited it should be remov...

Страница 27: ...e 7 2 Reduce the temperature by suitable means gas resp liquid channels are closed disassembly the pump and especially clean the channels mechanical seal is leaking change mechanical seal pump does no...

Страница 28: ...200 compression pressure mbar 2500 2200 2200 gas entry temperature r dry vapour saturated 160 C 80 C speed min 1 VZ 110 180 50Hz 60 Hz 1450 1750 service liquid temperature 10 C 60 C density 1200 kg m3...

Страница 29: ...2 Mise en Place 32 5 3 Tuyauteries 33 5 3 1 Tubulure d aspiration 33 5 3 2 Tubulure de refoulement 33 5 4 Branchement lectrique 33 5 5 Modes de fonctionnement 34 5 5 1 R frig ration par circulation ou...

Страница 30: ...e monteur et le personnel sp cialis l exploitant avant le montage et la mise en service et qu il soit toujours disponible sur le lieu de la pompe de l installation En plus des r gles de s curit mentio...

Страница 31: ...ue doit tre exclu pour les d tails consulter les prescriptions sp cifiques du pays ainsi que celles des usines d lectricit locales 2 6 Instructions de s curiti pour l entretien inspection et travaux d...

Страница 32: ...cr un effet de compression impulsions r duites Il est necessaire d alimenter resp refrig rer continuellement le liquide de service norma lement de l eau Il dissipe la chaleur de com pression cr e et...

Страница 33: ...un clapet anti retour devrait tre install afin d viter que la conduite vide se rempli avec liquide de service resp afin d viter une chute de pression dans le syst me vide S il y a un organe d arr t va...

Страница 34: ...disponible en quantit suffisante et que l on n attache pas d int r t au recyclage du liquide de fonctionnement Si le gaz et le liquide ne doivent pas obligatoi rement tre vacu s s par ment on peut ren...

Страница 35: ...rin age UL Raccord pour robinet d a ration Sch ma d installation Refroidissement par circulation en circuit ouvert Fig 3a S parateur mont s par ment Fig 3b S parateur rapport Fig 3c R gulation thermo...

Страница 36: ...MODE D EMPLOI 36 Refroidissement en circuit ouvert Fig 4a S parateur mont s par ment Fig 4b S parateur rapport Fig 4c R servoir avec robinet flotteur...

Страница 37: ...MODE D EMPLOI 37 Refroidissement par circulation en circuit ferm Fig 5a S parateur mont s par ment Fig 5b S parateur rapport Fig 6 Emplacement du raccord d eau de fonctionnement...

Страница 38: ...e d arr t VK est ouverte Arr ter les robinets de r glage dans leur position Afin de contr ler le niveau de liquide N on peut raccorder une vanne au raccord Ue3 Une vanne de vidange automatique dans ce...

Страница 39: ...ique indiqu dans les prospectus et catalogues est obtenu pour une temp rature d eau de fonc tionnement de 15 C Un fonctionnement une temp rature d eau de fonctionnement plus lev e se traduit par une r...

Страница 40: ...u par le raccord de protection de cavitation une petite quantit de gaz qui ne condense pas la compression Ceci peut s effectuer par un robinet d a ration h une conduite remontant d environ 300 mm avec...

Страница 41: ...onter la pompe et nettoyer les canalisations Garniture m canique non tanche Remplacer la garniture m canique La pompe n atteint pas le vide voulu pression d bit D bit d eau d coulement A trop petit V...

Страница 42: ...de compression mbar 2500 2200 2200 temp rature d aspiration du gaz sec 160 C satur en vapeur d eau 80 C VZ 110 180 vitesse de rotation min 1 50Hz 60 Hz 1450 1750 anneau liquide temp rature 10 C 60 C p...

Страница 43: ...billes 330 Lagertr ger Bearing housing Corps paliers 360 1 2 Lagerdeckel Earing cover Convercle de roulement 411 1 3 Dichtring Joint ring Garniture d tanch it 412 O Ring o ring Joint torique 441 Geh...

Страница 44: ...MODE D EMPLOI 44 VZ B...

Страница 45: ...MODE D EMPLOI 45 VZ G...

Страница 46: ...MODE D EMPLOI 46...

Страница 47: ...MODE D EMPLOI 47...

Страница 48: ...05 Adresse SPECK PUMPEN Walter Speck GmbH CO KG Regensburger Ring 6 8 D 91154 Roth Tel 49 09171 809 0 Fax 49 09171 809 10 e mail info speck pumps d internet http www speck pumps de Vervielf ltigung je...

Отзывы: