1-8 (E)
Digital Cinema Dual System
1-5. Installation
Flow
The installation procedure for this system is shown in the flow chart.
For the details of each flow, refer to the corresponding item.
n
Basically there is no problem even if Sections 2-1 to 2-4 are not performed in sequential order. However,
do not connect the power cord in Section 2-5 before Sections 2-1 to 2-4 are completed.
Start the installation.
Install the projector.
(Refer to Section 2.)
.
2-1. Installation of Duct
.
2-2. Installation of Lens
.
2-3. Installation of Lamp
.
2-4. Installation of Touch Panel Monitor
.
2-5. Connection of Power Cord
.
2-6. Adjustment of Projector Tilt
.
2-7. Installation of Dual System Accessory Kit (LKRA-010)
.
2-8. Installation of 3D Filter and Holder (LKRA-011)
.
3-1. Installation of Server
.
3-2. Connection with Projector
.
3-3. Power Connection
.
3-5. Installation of CRU DATAPORT Carrier
.
5-1. Update to Dual System Software
.
5-2. System Startup and Login
.
5-4. Initial Setting
.
5-5. Performing the Marriage
.
5-6. Projector Startup
.
5-7. Image Adjustment Flow
.
2-8-4. Check/Adjustment of 3D Filter Position
.
5-8. Image Adjustment
.
5-9. Color Space Conversion (CSC) Adjustment
.
5-10. Check of Video Signal and Audio Output
.
5-11. Network Setting
.
5-12. Folder Setting
.
5-13. Setting of External Equipment
.
5-14. Other Settings
.
5-15. Operating This System Using a Personal Computer (PC)
.
5-16. Shutdown
Install the server.
(Refer to Section 3.)
Connect the external equipment.
(Refer to Section 4.)
Setting and adjustment
after the connection.
(Refer to Section 5.)
Connect with the 4D system.
(Only when it is required)
(Refer to Section 7.)
Installation/Adjustment of the
LKRA-PCAB1
(Refer to Section 6.)
The installation is completed.