DKC400Y AC Sliding Gate Installation Manual www.solavis.com.au
Copyright © 2008 SOLAVIS
™
Doc: DKC400Y Installation Manual v1.1 page 7 of 22
Concrete pad
The base of the unit should be installed on a concrete slab/pad to ensure proper stability.
The concrete pad should be approximately 300mm x 200mm x 200mm deep to ensure
proper operation.
Anchors
You can use the anchors, bolts, washers and nuts that are provided with the operator.
These anchors must be set into the concrete when it is poured. You can also use other
ground anchors such as
Dynabolts
™
to install in existing concrete.
Operator
In locations where frost occurs, mount the gate operator on an installation pad as shown in
Fig.2. Check the operator and make sure it is lined up with the gate.
Nut
Bolt
Anchor
Nut
Spring washer
Plain washer
Gear
Gate operator
Installation pad
Conduit
Wires
Fig.2