Communication settings can be configured only after communication connections are
complete. Refer to
Setting Up Communication with the Monitoring Platform on page 60.
Select
Monitoring Communication
to configure communication with the
monitoring platform.
Select
Site Communication
to configure communication between multiple
SolarEdge devices or external non-SolarEdge devices, such as batteries or loggers.
Configuring Communication with Other Devices on page
54 below.
Power Control
The Grid Control option may be disabled. Enabling it opens additional options in the
menu.
The Energy Manager option is used for setting power export limitation, as described in
the
Export Limitation Application Note, available on the SolarEdge website at:
https://www.solaredge.com/sites/default/files/export_limitation_application_note_
.
https://www.solaredge.com/sites/default/files/application_
note_p_q_diagram_of_se_inverters_en_and_na.pdf
NOTE
SolarEdge inverters with “Grid Support” functionality (as marked on the
inverter certification label), are compliant with UL 1741 Supplement A. The
functionality is built into the inverter and no additional external device is
required.
Step 3: Verifying Proper Activation and
Commissioning
1. Select
Information
and verify that the correct firmware versions are installed on each
inverter.
2. Select
Status
and verify that inverter is operating and producing power.
3. Verify that additional configurations were properly set by viewing the relevant
Status screens.
4. Verify that the green inverter LED is steadily lit.
Your SolarEdge power harvesting system is now operational.