Final connections:
Refrigeration system; Water and drain system;
Electrical supply.
All technical installation work must be performed
by authorized professionals who are certified in
accordance with national legislation. The
refrigeration system is constructed in accordance
with the international Pressure Equipment
Directive (PED).
The electrical system is constructed in accordance
with the international Low Voltage Directive.
Connecting the refrigeration pipe to the
external refrigeration system:
Pipes, copper, are sealed and delivered under
moderate pressure (0.5 bar).
When opening, observe whether the pipe
is still under pressure. If not, contact your
Smeva partner.
See the floor plan for the correct positions
of the connections.
Diameter and cooling capacity depend on
display case length (see machine sticker and
product data sheet).
Make sure the external refrigeration
system is charged with the correct refrigerant
and matches the information on the type plate
of the display case
.
Connecting the water supply:
The display case is fitted with a ¾” female
adapter. Install a ¾” male shut-off valve with non-
return valve (if equipped with humidification).
Shut-off valve with 3/4” male adapter with
non-return valve
(not included)
.
Preparations for optional water system
provided under substructure: Ø6 mm and
Ø10 mm plastic lines with quick connects.