96/148
Siemens Building Technologies
Commissioning instructions OZW775 V2.01
CE1C5663en
HVAC Products
Further commissioning steps
22.06.2012
5.4.3 Set meter readings
•
Select
Applications > Popcard…
and then operating page "Meter 1".
•
Double-click data point "Meter reading current" to open the dialog box, set the
required value and click
OK
to enter the value.
5.4.4 Set the number of operating hours
•
Select
Applications > Popcard…
and then operating page "Operating hours 1".
•
Double-click data point "Operating hours" to open the dialog box, set the required
value and click
OK
to enter the value.