5 General functions, fundamentals
05.02.2007
The changeover time used is the same time as that used for the pump / mixing valve
kick (kick day and kick time).
Main menu > Commissioning > Settings > …
or
Main menu > Settings > Protective functions
Operating line
Range
Factory setting
Kick day
Monday…Sunday
Monday
Kick time
00:00…23:59
10:00
Automatic changeover takes place after 168 hours (7 days) or – after a new start of the
plant – when kick day and kick time are reached.
Kick day and kick time for pump changeover remain valid even if the pump kick has
been deactivated.
The change from one pump to the other can take place as follows, depending on the
application:
•
With no interruption
•
With overlapping
•
With interruption
The change from pump A to pump B takes place instantly:
31
3
1D
42
A
B
The change from pump A to pump B is made with temporal overlapping, e.g. to ensure
a low noise level during changeover. The pump to be deactivated overruns for the
adjusted period of time:
31
3
1D
43
A
B
The change from pump A to pump B is made after a certain pause, e.g. to prevent
surge voltages or excessive water pressures:
31
31
D
44
A
B
Depending on the changeover priority, the pump kick will act as follows:
Impact of pump kick
Operating state of the
pumps
With automatic changeover
With fixed assignment
Both pumps do not run
(summer operation)
Kick first acts on the pump that
was in operation last
Kick first acts on the
reserve pump and then on
the working pump
One of the 2 pumps
runs
Not applicable
Kick only acts on the
reserve pump
The changeover delay also acts with pump kicks.
Changeover time
Changeover period
No changeover
delay
Changeover with
negative delay
Changeover with
positive delay
Pump kick