Commissioning via the built-in BOP
5.6 Function commissioning
SINAMICS V20 Converter
112
Operating Instructions, 10/2019, A5E34559884-012
Function diagram
Description:
The hammer start mode is enabled when an ON command is issued, and the following
sequence is performed:
●
Ramp up to P3354 Hz with the boost level specified by P1310, P1311, and P1312
●
Revert boost level to that specified by P1310, P1311, and P1312
●
Revert to "normal" setpoint and allow output to ramp using P1120