If the length of the hybrid cable is adequate for the installation:
1) For all power cables, leave 23.62 in. (600 mm) from where the double-layer sheath has
been peeled off and cut the excess length off.
2) Unsheathe the end of the power cable wire at 0.59 in. (15 mm) length.
3) Using a conduit, insert the hybrid cable’s power cable and optic cable together into the
cabinet. Be careful not to damage the optic cable’s connector.
4) From the inside of the cabinet, pull the optic cable to the right side of the system and
attach temporarily with a cable tie.
5) Using a flat-head screwdriver (-, 1x100), turn the RRH power terminal’s screw
counter-clockwise 2 to 3 times.
6) Insert the power cable to the terminal according to its usage and polarity, then fasten
the screw.
7) Bind two cables (-48 V, RTN) at 3.94 in. (100 mm) from the terminal using a cable tie.
8) Bury the optic cable following the system’s inner-right wall up to the UADU#0 side
and bind using a cable tie.
9) Connect the connector of the optic cable to UADU’s designated port. (Loop the optic
cable’s excess length respecting the bending radius ‘R=4.33 in. (110 mm)’, and arrange
it in the cable tray box. Be careful not to damage the optic cable during other works.)
Figure 2.23 Connecting Hybrid cable (1)
[Baseband Rack Right View]
RRH Power Terminal
Double-layer Sheath
Peel-off Point
23.62 in. (600 mm)
RRH CPRI Cable
(Optic Cable)
Flexible Pipe (2 in.)
Max. 39.37 in. (1,000 mm)
Butyl Rubber Tape
Hybrid Cable
DC Power Cable
Содержание Smart MBS RRH-P4
Страница 1: ...Ver 2600 00CTEIGAA 4 0 Smart MBS RRH P4 Installation Manual ...
Страница 116: ...Ver ANNEX B Feeder Line Work B 10 SAMSUNG Electronics Co Ltd 2600 00CTEIGAA 4 0 This page is intentionally left blank ...
Страница 158: ...Ver ANNEX F Standard Torque F 2 SAMSUNG Electronics Co Ltd 2600 00CTEIGAA 4 0 This page is intentionally left blank ...