14
M0627-1 version 3.3
3.1.2 Every six-months or 250,000 tool changes
The following maintenance activities should be carried out every six-months or after every 250,000 tool
changes, whichever comes first.
Activity
Equipment
Description
Cleaning
and
lubrication
Tool changer
Locking balls
Clean locking balls and add new
lubrication, (section 3.2.3).
Guide pins
Clean guide pins and add new
lubrication (section 3.2.3).
Air sealings
Clean sealings (section 3.2.3).
Spring-loaded pins
Clean spring-loaded signal pins (section
3.2.3).
Signal and servo
power sockets
Clean around the sockets and add new
lubrication (section 3.2.3).
High voltage sockets
Clean around the sockets and add new
lubrication (section 3.2.3).
Tool attachment
Locking cavities
Wipe cavities of locking balls clean
(section 3.2.4).
Guide holes
Clean the holes for the guide pins and
add new lubrication (section 3.2.4).
Signal and servo
power pins
Clean and servo power pins (section
3.2.4).
High voltage pins
Clean high voltage pins (section 3.2.4).
3.1.3 To replace when damaged or worn-out
Equipment
Description
Tool changer
Air sealings
See section 4.3.1 or 4.3.2
Guide pins
See section 4.3.3
Spring-loaded signal pins
See section 4.3.4
Signal interface
See section 4.3.5
Servo power interface
See section 4.3.5
High voltage interface
See section 4.3.5
Air module
See section 4.3.5
Tool attachment
Signal interface
See section 4.3.6
Servo power interface
See section 4.3.6
High voltage interface
See section 4.3.6
Air module
See section 4.3.6
O-rings
See section 4.3.7
Содержание P1301A
Страница 2: ...2 M0627 1 version 3 3 ...
Страница 34: ...34 M0627 1 version 3 3 ...
Страница 35: ...M0627 1 version 3 3 35 ...
Страница 36: ...36 M0627 1 version 3 3 ...