4.5.
Preparation for start up
DANGER: The following operations must out be carried only by qualified and specifically trained
technicians. The Manufacturer declines all responsibility for operations carried out without
respecting the safety regulations, by unqualified operators and without compliance with the
specifications of this manual.
ATTENTION: During operations, the operator must use all the necessary Personal Protective Equipment
(PPE).
Before bringing the partly-completed machine to full capacity, a number of preliminary checks are necessary to
be carried out at start-up.
Check valves
Make sure that all the valves on the partly-completed machine and on the system are open, that the service
valves are closed and that they all are fitted with caps.
Check utilities thermostatic valves
Make sure that all the electronic thermostatic valves of the utilities are correctly programmed.
ATTENTION: The positive and negative utilities must have a minimum overheating of 5K and a correct
MOP value on the expansion valve control to avoid increasing the intake pressure in the event of
system shutdown. 35 bar - 1°C is recommended.
Pre-heating of the compressor casing (if present)
At least 12 hours before starting the compressors, the casing heater must be energised to eliminate the risk of
diluting the lubricating oil with the refrigerating fluid.
Electronic control
To start the system it is necessary to follow this sequence of operations:
x
Set the disconnector (1) of the electrical panel to ON to supply the entire system;
x
Set the electronic control to ON via the display (2);
x
Using the display (2) carry out the operations indicated .