4.
Transport and Installation
DANGER: The operations indicated below must be carried out by qualified operators. The
Manufacturer declines all responsibility for operations carried out without respecting the safety
regulations, by unqualified operators and without compliance with the specifications of this manual.
ATTENTION! The user, having purchased the equipment, before use, becomes the person in charge
of the component subject to Directive 2014/68/EU (PED) and must arrange for the legal checks to
be performed according to the national legislation in force (Ministerial Decree 329 dated 1/12/2004
for Italy). For instance the start-up report, periodic checks, etc.
ATTENTION: With R744 (CO2) refrigerant all operations must be carried out only by specialist
technicians trained to operate with this type of refrigerant.
Prior to incorporating the partly-completed machine into the final equipment prepare the power supplies and
the appliances necessary for correct operation of the system, following the instructions provided in this
chapter and, if necessary, consulting the manufacturer's technical office beforehand.
4.1.
Environmental requirements
Regarding the installation zone, the system does not have any particular restrictions from an environmental
temperature viewpoint. The temperature can vary between -10°C ÷ +40°C.
The relative humidity must not exceed 50% with an ambient temperature of 40°C; higher relative humidity
levels are permitted for lower temperatures (example RH 90% with an ambient temperature of 20°C).
The machine cannot be installed over 1000 m above sea level, unless otherwise specified.
The partly-completed machine has been engineered and manufactured to work in environments where no
potentially explosive atmosphere is present.
4.2.
Power Supplies and Utilities
The power supplies and utilities (responsibility of the purchaser) necessary for operation of the partly-
completed machine consist exclusively of power supply.
Unless otherwise specified, the Purchaser must:
x
prepare the means necessary to transport the partly-completed machine to the assembly or
installation place;
x
prearrange the tools necessary for assembly and installation;
x
provide the auxiliary equipment and consumables (use only water and cleaning cloths).
4.3.
Transport and handling
The indications contained in this paragraph must be respected during the phases of transportation and
handling of the partly-completed machine and during its assembly on the final machine.
ATTENTION: During operations, the operator must use all the necessary Personal Protective Equipment
(PPE).
DANGER: During transportation or handling of the partly-completed machine it is necessary to follow the
warnings listed below.
x
The means used for lifting and transportation must be sized and suitable to the load being moved.
x
During the transportation phase, check that the load is correctly balanced and that there are no
parts that are not correctly fixed or at risk of damage.
x
The structure of the partly-completed machine must be intact and completely assembled.
x
Check that the area intended for handling is clear and that there are no obstacles that could
generate a dangerous situation.
x
Transiting and remaining under suspended loads is prohibited. Always place the partly-completed
machine on bearing surfaces suitable to support its weight.