Installation & Servicing Instructions Rinnai E-Series
17
- Boiler
system
fl
ushing (Not Boiler heat exchanger)
When replacing an existing boiler the heating system should be fl ushed with
the old boiler in place before the new boiler is added to the system. If the old
boiler has already been removed a bypass must be piped in when the new boiler
is installed in order to facilitate the fl ushing of the system.
The boiler must be valved off from the system, while the system is fl ushed. No
system cleaner should ever enter the boiler heat exchanger due to its caustic
nature which could damage the heat exchanger.
1. Close the shutoff valves on both the supply and return connections on the plumbing
kit (V1 and V2).
2. Open the bypass valve (V4).
3. Connect pump outlet hose (H1) to the purge station (BD1) and connect H2 to the
inlet of the pump and place the other end in the pail.
4. Connect drain hose (H3) to the return side purge station (BD2).
5. Pour the system cleaner into a pail and follow the system cleaner instructions on
circulation time and volume to be added to the system.
6. Close the valve (V3)
7. Operate the pump (P1) and circulate the cleaner through the system for required
time as established by the cleaner manufacturer.
8. Once the time required by the system cleaner manufacturer has been met place
the hose (H3) in a drain.
9. Close the purge station (BD1)
10. Open the auto feed on the system (F1) and allow water to rinse the system for
whichever is greater; 10 minutes or the required rinse time by the system cleaner
manufacturer.
Boiler system fl
ushing
fi g. 7
T
P
P
System cleaner
V1
V2
V4
V3
F1
BD1
BD2
CP
H2
H1
H3
Содержание E50C
Страница 43: ...Installation Servicing Instructions Rinnai E Series 43 electrical ladder diagram figure 23a ...
Страница 84: ...Installation Servicing Instructions Rinnai E Series 84 ...
Страница 127: ...Installation Servicing Instructions Rinnai E Series 127 Schéma électrique en échelle figure 23a ...