7.8.7 Final assembly
Dismantle trial assembly for determining the bearing
play again and perform the final assembly.
With the O-ring
412/3
With the distance ring
504
With 1 drop of adhesive on the shaft thread, e.g.
Loctite 243 from Loctite or an equivalent.
Only one drop of the adhesive is to be applied per
thread.
Otherwise the next dismantling operation will be more
difficult or no longer possible without destroying
components.
Install plain bearing pedestal
339
and tighten hex.
screws
901/5
.
Strong axial forces are again produced when
the completely assembled plain bearing
pedestal is inserted into the lantern.
Push the entire slide-in unit with housing (casing)
gasket
401
into the housing (casing)
100
and
screw together with hex. screws
901/3
.
When tightening the housing (casing) screws
901/3
,
make sure that the support bracket
183
is firmly
positioned. If necessary, undo support bracket, align
and secure again.
For tightening torques, see
Section 1.1
.
7.8.8 Fill bearing pedestal with oil
Oil quantities:
For group 1
appr. 17 oz (500 ml)
For group 2
appr. 50 oz (1460 ml)
Groups see
Section 1
.
Type of oil:
See
Section 7.2.2
.
Procedure for filling with oil:
Tilt constant level oiler
638/1
.
Fill the oiler with oil.
Swing the constant level oiler into the vertical
position.
If the oil level still falls too much, pour more oil into
the oiler.
Fig. 6
7.9 Tests
The pumps are tested with water at the
manufacturer's.
The operating data measured are documented in a
works certificate
.
If, during a test after repairs, discrepancies compared
with the works certificate are discovered, the following
people can be called in:
1. in-house pump office
2. The manufacturer Richter
or its local agent
The following conveying data can be checked using
the
pump performance curves
:
Flow rate
Head
Power requirement
NPSHR