Commissioning
Servitec 35-120 with Touch controller — 06.07.2016 - Rev. B
English — 39
7.3
Modifying the controller's start routine
Note!
During commissioning, you must once execute the start routine.
•
For information about controller operation, see chapter 9.1 "Operator panel" on page 51 .
7.4
Filling the device with water and venting
1. Use the facility system to fill the device.
– After you have opened the "DC" ball valves, the
vacuum spray tube will autonomously fill if the
facility system provides sufficient water.
2. Optional
– Use the feed and drain cock to to fill water into
the device (3).
– Connect a hose at the feed and drain cock (3) of
the "VT" vacuum spray tube.
3. Fill the vacuum spray tube with water.
– Air escapes via the degassing valve (2) and the
water pressure can be read at the vacuum gauge
(1).
1 "PI" vacuum gauge
5
"PU" pump
2 "DV" degassing valve
WC Make-up line
3 "FD" feed and drain cock
DC Degassing lines
4 "AV" vent screw