Peri SKYDECK Скачать руководство пользователя страница 55

53

2.7

45.1

A9 SKYDECK platforms

Platform installation

 

Risk of falling!

 

– Cantilevers should not have form-

work erected or be stepped on be-
fore being firmly secured with ten-
sion chains.

 

– When lingering on the slab form-

work, measures must be taken to 
prevent falling, e.g. PPE.

 

– Clearly mark unsecured building 

edges!

Begin with the platform assembly in 
one area in which there is no risk of  
falling to the rear or at the side (e.g. 
Area II, see Ground Plan Fig. A9.01).

1. With the help of the Erection Aid 

SSH, access the recess of the plat-
form decking and pull the platform 
out from its safe position. (Fig. A9.12)

2. Move the platform into position at an 

angle from above in front of the last 
panel onto the cantilevered main beam.

3. By further lowering the platform, pos-

itive assembly is carried out:

 

– The slide (45.1) on the underside of 

the platform is secured when posi-
tioned in the platform support (2.7) on 
the Main Beam SLT 375. (Fig. A9.12a)

 

J

The platform is locked in position 
and secured against tipping.

 

– The slide safety device locks into 

the teeth of the main beam.

 

J

The platform is secured against 
moving in the longitudinal 
direction of the beam. 

4. Detach both crane hooks. Site per-

sonnel must wear personal protection 
equipment (PPE) to prevent falling!

 

– Crane eye swivels downwards and 

the securing hook grips under the 
self-draining edges of the main 
beam. If necessary, press down 
the crane eye.

 

J

The platform is additionally 
secured against tipping and 
lifting. (Fig. A9.12b)

5. Install other platforms in the same 

way with the shuttering aid.

6. Close infill areas < 75 cm using con-

tractor’s own resources, e.g. scaffold 
planks 24 x 4.5 cm.

Fig. A9.13

Fig. A9.12a

Fig. A9.12b

Securing hook

Shuttering Aid 
SSH

Self-draining 
edges

Anti-slip device

7. Handrails for infill areas are created 

using handrail boards 3 x 15 cm and 
toe boards (use nail holes in platform 
guardrails) or standard couplings and 
scaffold tubes.

For difficult assembly situations, e.g. 
wind, guide the platform with 2 shutter-
ing aids. (Fig. A9.13)

Fig. A9.12

SKYDECK Panel Slab Formwork

Instructions for Assembly and Use – Standard Configuration

SKYDEKC AuV_ex_791458.indb   53

13.12.16   16:57

Содержание SKYDECK

Страница 1: ...SKYDECK Panel Slab Formwork Instructions for Assembly and Use Standard Configuration Edition 09 2016...

Страница 2: ...he inner bay 39 Transfer of horizontal loads from a casting segment 40 A8 Cantilevers Guardrails 42 Bracing on leading edges to prevent tipping 42 Guardrails with Handrail Unit SD 43 SKYDECK Guardrail...

Страница 3: ...1 2 1 4 3 1 2 3 4 SKYDECK Panel Slab Formwork Instructions for Assembly and Use Standard Configuration Overview Main components 1 Drophead SFK 2 Main Beam SLT 225 3 Panel SDP 4 Cover Strip SAL...

Страница 4: ...Dimensions are usually given in cm Other units of measure e g m are shown in the illustrations Load details are usually given in kg Other measurement units e g t are specified in the illustrations Co...

Страница 5: ...ed out the quali fied persons must have received in structions which contain at least the following points Explanation of the plan for the assem bly modification or dismantling of the formwork in an u...

Страница 6: ...il unit that is screwed to the supporting frame as a framed construction and held by a securing lever when opened up The platform can be used on the edge of the floor slab as well as in the corner tab...

Страница 7: ...ally blocked with concrete are freed by means of a steel pin from the formlining side When placing bundles of reinforcement bars or other heavy objects on horizon tally stored formwork elements suita...

Страница 8: ...mediately create another risk assessment with appropriate measures for en suring the stability of the formwork system being carried out based on the results and arrange for an extraordinary in spectio...

Страница 9: ...pplied by the contractor e g bracing Load assumptions for horizontal loads in accordance with DIN EN 12812 When storing heavy items on the form work the load bearing capacity must be taken into consid...

Страница 10: ...ng lifting gear using the four load bearing points Transport PERI pallets and stacking devices are suitable for lifting by crane or forklift They can also be moved with the PERI Pallet Lifting Trolley...

Страница 11: ...sequence 1 Open locking mechanism on the pal let frame 2 Slide in one handrail unit and close locking mechanism 3 Slide in additional handrail units Handrail units lock automatically above the red ba...

Страница 12: ...ks of up to 5 elements Weights SDB 300 184 kg piece SDB 225 155 kg piece SDB 150 108 kg piece Stacks of platforms can be lifted with a fork lift truck using the long side Fig A1 09 The stack can be mo...

Страница 13: ...37 5 Panel SDP 75x75 Panel SDP 75x50 Panel SDP 75x37 5 Cover Strip SAL The Cover Strip SAL is available with the following dimensions Cover Strip SAL 150 Cover Strip SAL 75 Cover Strip SAL 50 Cover St...

Страница 14: ...DIN EN ISO 4016 M12 x 40 4 6 galv Mu Preparing the Drophead 1 Push drophead wedge 1 1 and Drop head 1 2 upwards as far as possible Fig A2 06 2 Insert drophead wedge 3 Secure with hammer blow shutter i...

Страница 15: ...K Platform SDB 150 SKYDECK Platform SDB 225 SKYDECK Platform SDB 300 Fig A2 09 Fig A2 10 Internal crane eye Internal crane eye retracted Preparation for Use Take individual platforms from the stack fo...

Страница 16: ...of proof Rk characteristic resistance Rd design value of the resistance Fk Factual actual or characteristic action Ed design value of the action Fult Rk characteristic resistance e g breaking load Fpe...

Страница 17: ...g operations 1 of the vertical load DIN EN 12812 8 2 2 2 Horizontal load from the tilting position 1 of the vertical load DIN EN 12812 9 3 4 2 Wind loads Working wind dynamic pressure qW A 0 20 kN m D...

Страница 18: ...r Assembly and Use Standard Configuration A3 System dimensions Overview of the required frames MRK with the use of MULTIPROP Towers PRK with the use of PEP Props Frames MRK Item no PRK Item no SKYDECK...

Страница 19: ...beam connec tion 2 1 must be mounted in the middle of the beam support 1 2 of the SKYDECK heads Fig A4 02a A4 02b A4 02c 6 Secure Main Beam SLT 225 2 with Wall Holder SWH 2 8 7 Position second pair of...

Страница 20: ...formwork surface area may only be accessed or loaded when Wall Holders SWH 2 have been installed The Wall Holder SWH 2 8 is used to hold the slab formwork in a horizontal position during the assembly...

Страница 21: ...cing 2 275 m 4 Insert Main Beam SLT 225 2 into the beam support of the Prophead and Drophead Fig A4 09 5 Secure with tripod 6 Insert panels 3 Fig A4 10 J JThe transverse bay is complete Fig A4 11 Shut...

Страница 22: ...lete Fig A4 14 The Wall Holder SWH 2 8 is mount ed in every second bay Risk of falling When lingering on the slab form work measures must be taken to prevent falling e g PPE When shuttering from below...

Страница 23: ...26 km h and dy namic pressure 0 061 kN m 36 km h For unfavourable structure geometries or larger wind speeds additional secur ing measures are to be implemented e g ballast bracing Fig A4 16 dismantl...

Страница 24: ...ray the forming area with a release agent also from below if used for the first time Risk of slipping The forming area becomes slippery through the use of release agents Be extremely careful when acce...

Страница 25: ...23 SKYDECK Panel Slab Formwork Instructions for Assembly and Use Standard Configuration...

Страница 26: ...stall Filler Timber SPH 12 vertically or horizontally to the Combihead SCK Fig A5 04 nailed laterally on the panel horizontally transverse to the sus pended Edge Beam SRT Fig A5 05 A5 06 End Support S...

Страница 27: ...SL 11 Fig A5 14 Mounting the main beam The Main Beam SLT must be mounted in the middle of the beam support of the SKYDECK Heads The main beam connection 2 1 encloses the main beam support 7 1 of the h...

Страница 28: ...ent positions Select support posi tion according to the compensation width Position the cantilever of the Combihead SCK as close as possible to the wall in order to provide maximum support for the inf...

Страница 29: ...19 A Install the cantilever of the Combihead 7 up to the compensation area Fig A5 19 B In the system with the Drophead 1 the Combihead 7 is always installed trans versely if it is positioned under a c...

Страница 30: ...and secure in posi tion with nails Longitudinal compensations Secure filler plates with nails Drophead infills up to 2 25 m 5 cm Prophead infills up to 2 25 m Length of room minus n x 2 30 m 2 25 m c...

Страница 31: ...d by the contractor Gap 5 12 5 cm 1 Place Main Beam SLT 2 on inset prop with Combihead SCK 7 or Prophead SSK 6 2 Place additional props with trans versely positioned Combiheads SCK 7a in an offset arr...

Страница 32: ...tall End Support Filler Timber and Edge Beam 3 Install formlining and secure in posi tion with nails Fig A5 26 A5 27 Fig A5 26 Fig A5 30 Fig A5 27 Gap 20 75 cm 1 Install Main Beam in Drophead SFK 1 Fi...

Страница 33: ...xt prophead with Panel SDP 75 x 75 3a Fig A5 31 A5 32 2 Depending on the required load bear ing capacity continue forming with filler panels See PERI Tables 3 Form gaps up to 75 cm see following pages...

Страница 34: ...ler Timber SPH 12 or timber 13 up to max 6 cm on the panel Fig A5 36 3 Install formlining 16 and secure with nails If panels 3 are placed over the main beam 2 the panel edge can not laterally stabiliz...

Страница 35: ...he infill 2 Install Panel 3 3 Install Edge Beam SRT 2 9 or Filler Timber SPH 12 in the Combihead 4 Install formlining 16 and secure with nails Fig A5 37 Alternatively 1 Place Panel SDP 3 over the Main...

Страница 36: ...ing around columns Take into account the supporting direction of the formlining Alternatively Install Edge Beam SRT 2 150 9 in a suspended position Fig A6 03 Flatly position Filler Timber SPH or in st...

Страница 37: ...e Beam 9 in a sus pended position Fig A6 05 A6 06 Maximum column dimensions x 130 cm y 138 cm Depending on the slab thickness and prop width the transverse positioned filler plates are to be additiona...

Страница 38: ...of influence of flat Filler Timber SPH maximum deformation l 500 For other slab thicknesses the values are interpolated linearly Take into account the supporting direction of the formlining Fig A6 10...

Страница 39: ...ot desired Fig A6 11 Fig A6 12 Additional formlining support depending on the situation on site Shifting the main beam axis Fig A6 13 Secure Main Beam SLT props that have been shifted with tripods In...

Страница 40: ...nsferred H 4 92 kN This load must be verified by the struc tural engineer regarding the respective column in the actual building condition Fig A7 01 Transfer of horizontal loads into the columns of th...

Страница 41: ...gs Bays must be braced longitudinally and horizontally Assembly 1 Mount Base Plate on a sufficiently load bearing surface area e g using PERI Anchor Bolt 14 20x130 Item no 124777 Take into considerati...

Страница 42: ...ation LFK 2 Storm 1 x Hload edge area 9 x Hload inner bay H 1 291 kN 9 x 0 033 kN 1 588 kN Number of chains H 1 588 kN 7 307 kN LFK 1 Concreting is decisive nchain H perm tension force of chain 7 31 k...

Страница 43: ...60 1 5 kN Fig A7 04 Calculation Load Compilation LFK 1 Concreting 2 x Hload edge area stopendformwork pressure 8 x Hload inner bay H 2 x 2 447 kN 1 43 kN 8 x 0 54 kN 6 354 kN Load Compilation LFK 2 S...

Страница 44: ...to inner prop max 50 cm Brace using Anchor Chain 23 Base Plate 24 and Anchor Bolt 24 1 Fig A8 01 Max slab overhang 37 5 cm Cantilevers with SKYDECK Platforms SDB Fig A8 02 A8 03 See Cantilevers with P...

Страница 45: ...04a 1 Pull lug 25 1 upwards Fig A8 07 2 Move the Handrail Unit SD 25 firstly in the direction of the building edge l and then downwards ll Fig A8 04a 3 Place Handrail Unit SD with the hooks 25 2 betw...

Страница 46: ...h remove the top guardrail board Adapt working area ac cordingly to suit changed guardrail situa tion After the last row of panels mount the Guardrail Holder SGH for the End Guard rail Frame on all m...

Страница 47: ...45 SKYDECK Panel Slab Formwork Instructions for Assembly and Use Standard Configuration...

Страница 48: ...slab formwork in con nection with SKYDECK Platform SDB is carried out in four areas I IV The sequence must be maintained Fig A9 01 Risk of falling Ensure that end to end side pro tection is installed...

Страница 49: ...and formed into a base frame using MULTIPROP MRK 150 36 and MRK 225 36 1 Frames Fig A9 02 Mount the frame at the same level above the slab Locking wedges 36 2 are facing outwards 3 Attach two Prophea...

Страница 50: ...load distribu tion when directly reaching under with the transportation fork 1 Attach 2 timbers with min 8 12 225 40 supplied by contractor to the hex bolts using nuts and washers Fig A9 04 2 Diagonal...

Страница 51: ...table Follow Instructions for Use SKYDECK Lifting Fork 1 Raise the corner table using the SKYDECK Transportation Fork and extend the Props MP to the required length 2 Position the corner table at the...

Страница 52: ...ch two tension chains to the Tension Sleeves SAO Diagonally 23 2 ten sion the first tension chain the sec ond tension chain 23 3 is vertically tensioned Fig A9 07 A9 07a Risk of falling During assembl...

Страница 53: ...24 Fig A9 08 5 From below bay by bay immediately install 3 Panels 150 x 75 3 and 1 Filler Panel 150 x 37 5 3a as far as the platform support 2 7 of the Main Beam SLT 375 For example with the PERI Str...

Страница 54: ...ge Clips SPKK 20 Components 2 Main Beam SLT 225 2 6 Main Beam SLT 375 10 Edge Beam SRT 19 Timber 20 Panel Wedge Clip SPKK 45 SKYDECK Platform SDB 300 46 SKYDECK Platform SDB 150 47 SKYDECK Platform SD...

Страница 55: ...is locked in position and secured against tipping The slide safety device locks into the teeth of the main beam J JThe platform is secured against moving in the longitudinal direction of the beam 4 De...

Страница 56: ...J JThe securing hook is released 7 The platforms are now moved to the next place of use Fig A9 14 8 Loosen the tension chains in the edge area bays B C lower the drop heads or props remove panels and...

Страница 57: ...uptions such as columns offset walls or at an external wall Fig A9 16 The various platforms in use form a working and safety scaffold according to DIN 4420 Part 1 With 1 30 m platform width they fulfi...

Страница 58: ...rned 90 without having to assemble a new system As a result T and L shaped ground plans are possible The change of direction is realized using the Main Beams SLT 150 in the outer row of the main bay T...

Страница 59: ...of the transverse bay Fig A10 02 5 If a gap occurs with the Panel SDP between the transverse bay direction and main bay direction this is closed using filler timber 12 and filler plates 16 Fig A10 04...

Страница 60: ...in bay as well as the Frame MRK Required components per change of direction bays 1 Drophead SFK 1x 2 Main Beam SLT 225 1x 2a Main Beam SLT 150 225 1x 3 Panel SDP 150 x 75 1x 3 1 Panel SDP 150 x 37 5 1...

Страница 61: ...ig A10 06 Spacing bay width 1 50 m without Frame MRK see Section A4 Shuttering Install Panel SDP Insert panels in the direction of the main bay 1 Insert Panel SDP 150 x 75 3a 2 Insert Filler Panel SDP...

Страница 62: ...ssembly 1 Set up first bay with tripods or Frame MRK 2 Mount Base Plate 24 on a suffi ciently load bearing surface area e g using PERI Anchor Bolt 14 20x130 Item no 124777 Take into considera tion the...

Страница 63: ...14 20x130 Item no 124777 Take into considera tion the Technical Data Sheet 5 Insert the Tie Yoke of the Tension Unit Upper Part onto the Tie Rod 41 3 secure with the Hex Nut SW 30 50 42 and attach to...

Страница 64: ...ide there is a clearance of approx 6 cm Fig A12 01 Edge infills Striking takes place firstly on the trans verse infills and then the longitudinal infills Remove props and store in pallets Dismantle sy...

Страница 65: ...Strips SAL 4 remain standing Fig A12 05 Remaining areas Remove props on walls and store in pallets Remove filler areas around columns After reaching the required concrete strength lower drophead props...

Страница 66: ...ar room height formwork assembly height with Drophead 41 cm Direction of assembly Max panel span Selected prop Actual prop load according to PERI Tables zul St tzenlast nach PERI Tabellen Inner tube b...

Страница 67: ...016 0 879 70 19 82 5 402 0 684 6 347 0 016 0 909 75 21 08 6 152 0 727 7 145 0 016 0 938 80 22 30 6 930 0 769 7 968 0 016 0 967 85 23 53 7 754 0 812 8 838 0 016 0 996 90 24 75 8 623 0 854 9 753 0 016...

Страница 68: ...28 m 3 63 m 55 3 84 m 4 16 m 3 88 m 4 20 m 60 4 60 m 4 87 m 4 65 m 4 91 m A15 Inclined slabs Maximum permissible slab inclination with Tension Sleeve SAO and Chain 3 0 kN Considered horizontal loads...

Страница 69: ...30 5 kN 60 1 0 0 6 27 0 kN 8 1 kN 34 0 kN 6 5 kN 32 6 kN 4 9 kN 31 2 kN 30 1 0 0 6 31 2 kN 5 4 kN 33 9 kN 4 3 kN 33 4 kN 3 2 kN 32 8 kN 35 1 0 0 6 31 2 kN 5 7 kN 34 5 kN 4 6 kN 33 8 kN 3 4 kN 33 2 kN...

Страница 70: ...11 3 kN 36 8 kN 30 5 0 2 9 31 2 kN 12 6 kN 37 5 kN 10 1 kN 36 3 kN 7 6 kN 35 0 kN 35 5 0 2 9 31 2 kN 13 3 kN 38 9 kN 10 7 kN 37 3 kN 8 0 kN 35 8 kN 40 5 0 2 9 31 2 kN 14 3 kN 40 4 kN 11 4 kN 38 6 kN...

Страница 71: ...kN 21 0 kN 43 2 kN 16 8 kN 40 8 kN 12 6 kN 38 4 kN 40 9 0 5 1 31 2 kN 17 9 kN 42 7 kN 13 5 kN 39 9 kN 45 9 0 5 1 31 2 kN 14 6 kN 41 5 kN 50 9 0 5 1 31 2 kN 16 0 kN 43 5 kN 55 9 0 5 1 31 2 kN 60 9 0 5...

Страница 72: ...N 55 1 0 0 6 26 4 kN 6 9 kN 32 1 kN 5 5 kN 31 0 kN 4 1 kN 29 8 kN 60 1 0 0 6 26 4 kN 7 9 kN 33 3 kN 6 3 kN 31 9 kN 4 8 kN 30 5 kN 30 1 0 0 6 30 5 kN 5 3 kN 33 2 kN 4 2 kN 32 7 kN 3 2 kN 32 1 kN 35 1 0...

Страница 73: ...kN 55 5 0 2 9 26 4 kN 16 1 kN 39 6 kN 12 9 kN 37 0 kN 9 7 kN 34 4 kN 60 5 0 2 9 26 4 kN 18 5 kN 42 4 kN 14 8 kN 39 2 kN 11 1 kN 36 0 kN 30 5 0 2 9 30 5 kN 12 3 kN 36 7 kN 9 9 kN 35 5 kN 7 4 kN 34 2 k...

Страница 74: ...3 7 kN 18 1 kN 40 3 kN 13 6 kN 36 8 kN 55 9 0 5 1 26 4 kN 20 3 kN 43 0 kN 15 2 kN 38 9 kN 60 9 0 5 1 26 4 kN 23 3 kN 46 6 kN 17 4 kN 41 5 kN 30 9 0 5 1 30 5 kN 19 4 kN 40 2 kN 15 5 kN 38 3 kN 11 6 kN...

Страница 75: ...hen calculating the prop load the actual extension length may be used The exact extension length of the prop when using the SKYDECK drophead is clear room height minus 0 41 m Prop loads over 33 3 kN b...

Страница 76: ...6 A16 SKYDECK Prop loads with Prophead SSK When calculating the prop load the actual extension length may be used The exact extension length of the prop when using the SKYDECK Prophead is clear room...

Страница 77: ...count e g curing A minimum of 1 88 cm m Q 188 is required for the bottom reinforcement layer For systems without any centre support of the main beams a live load of 1 kN m on the slab which has struck...

Страница 78: ...0 86 0 37 0 95 0 82 0 35 1 00 0 78 0 33 1 05 0 75 0 32 1 09 0 73 0 31 0 20 0 30 0 40 0 50 0 60 0 70 0 80 0 90 1 00 1 05 1 09 GT 24 4 61 3 93 3 45 3 12 2 86 2 66 2 51 2 26 2 06 1 97 1 91 VT 20 3 89 3 3...

Страница 79: ...36 4 3 70 25 3 29 8 36 4 36 4 3 80 23 7 27 6 36 4 36 4 3 90 22 3 25 5 36 4 36 4 4 00 20 7 23 5 35 3 36 4 4 10 33 3 36 4 4 20 31 5 36 4 4 30 29 8 35 0 4 40 28 2 32 9 4 50 26 8 30 8 4 60 25 3 28 9 4 70...

Страница 80: ...9 34 3 35 3 35 3 3 80 21 3 23 5 28 2 31 8 35 3 35 3 3 90 19 8 21 9 26 5 29 1 35 3 35 3 4 00 18 3 20 1 24 8 26 9 35 3 35 3 4 10 23 2 25 3 35 3 35 3 4 20 21 8 23 5 35 3 35 3 4 30 20 4 22 1 34 6 35 3 4 4...

Страница 81: ...45 5 41 5 41 5 3 10 41 4 44 2 41 5 41 5 3 20 38 7 42 1 41 5 41 5 3 30 36 1 38 7 41 5 41 5 3 40 33 3 35 7 41 5 41 5 3 50 30 7 32 5 41 5 41 5 3 60 41 5 41 5 3 70 41 3 41 5 3 80 38 5 41 3 3 90 35 9 38 1...

Страница 82: ...8 43 8 44 1 40 3 40 3 3 30 31 1 33 2 41 7 44 1 40 3 40 3 3 40 28 5 30 3 38 8 41 8 40 3 40 3 3 50 26 1 27 1 37 1 39 7 40 3 40 3 3 60 34 8 36 5 40 3 40 3 3 70 32 4 33 5 40 3 40 3 3 80 30 0 30 9 40 3 40...

Страница 83: ...14 2 19 0 3 40 13 2 17 4 3 50 12 4 15 7 A18 Slab props PEP Ergo B Permissible prop load kN according to type test Extension length m Outer tube bottom Inner tube bottom Outer tube bottom Inner tube b...

Страница 84: ...27 8 40 0 40 0 4 00 21 4 25 3 40 0 40 0 4 10 39 0 40 0 4 20 36 3 40 0 4 30 33 8 39 0 4 40 31 6 36 7 4 50 29 6 34 3 4 60 27 8 32 1 4 70 26 1 30 1 4 80 24 5 28 2 4 90 23 0 26 4 5 00 21 4 24 7 A18 Slab...

Страница 85: ...45 4 50 4 3 7 42 1 47 4 3 8 39 1 43 7 3 9 36 2 39 8 4 0 33 1 35 3 A18 Slab props PEP Ergo B Permissible prop load kN according to type test Extension length m Outer tube bottom Inner tube bottom Outer...

Страница 86: ...9 43 5 4 90 45 2 42 4 5 00 42 5 41 3 5 10 39 9 39 9 5 20 37 2 38 5 5 30 34 9 37 1 5 40 32 8 35 6 5 50 30 8 34 1 5 60 29 3 32 6 5 70 27 8 31 2 5 80 26 4 29 6 5 90 25 1 27 9 6 00 23 8 26 2 6 10 22 7 24...

Страница 87: ...85 SKYDECK Panel Slab Formwork Instructions for Assembly and Use Standard Configuration...

Страница 88: ...For cantilevers 3750 240 1042 1042 450 750 375 375 750 450 82 266 12 300 300 061000 061011 061020 061010 061013 061030 15 500 11 700 9 780 8 560 6 350 5 250 Panels SDP Panel SDP 150 x 75 Panel SDP 150...

Страница 89: ...ring around columns Panel with 21 mm plywood 1500 750 49 1488 738 98 061026 061027 061024 061038 1 580 0 794 0 524 0 400 Cover Strips SAL Cover Strip SAL 150 Cover Strip SAL 75 Cover Strip SAL 50 Cove...

Страница 90: ...nd filler timber 305 250 259 161 50 061200 3 860 Prophead SSK With self locking coupling Supports main beams panels edge girders and filler timber 161 50 260 250 061210 6 180 Drophead SFK With self lo...

Страница 91: ...100 1490 1102 061021 061022 8 660 5 350 Triangular Frames SDR Triangular Frame SDR 150 x 75 Triangular Frame SDR 75 x 75 For compensations on inclined walls For compen sations with 21 mm plywood form...

Страница 92: ...r STV For assembling SKYDECK Slab Tables Also allows the fixing of intermediate props at the main beam 330 70 86 061280 0 778 Panel Wedge Clip SPKK Fixes panel on main beam 116 116 80 061290 0 133 Pan...

Страница 93: ...missible load 150 kg m2 2240 061060 108 000 Platform SDB 150 Work and safety scaffold Scaffold width 1 30 m With continuous 39 mm thick decking and foldable handrail frame Technical Data Permissible l...

Страница 94: ...Holder SGH Alu For assembling a guardrail with SKYDECK Technical Data Maximum width of influence 1 55 m 1500 245 368 300 5 300 1640 061260 6 150 Accessories Guardrail Post SGP 061062 185 000 Platform...

Страница 95: ...210 Anchor Bolt PERI 14 20 x 130 For temporary fixation to reinforced concrete structures Note See PERI data sheet Drilling 14 mm 130 SW 24 14 028100 1 830 Base Plate for RS For assembly of RS Push Pu...

Страница 96: ...Instructions for Use Technical Data Permissible load bearing capacity 1 0 t 1720 1973 1630 760 640 1510 061530 82 400 Pallet SD 150 x 225 galv For stacking and transportation of 48 SKYDECK Panels 150...

Страница 97: ...uctions for Use Technical Data Permissible load bearing capacity 1 0 t 3240 1429 2800 3900 1224 061510 105 000 Pallet Lifting Trolley 1800 mm For moving pallets and crate pallets Note Follow Instructi...

Страница 98: ...Item no Weight kg 035500 72 800 Stripping Cart Alu Mobile working scaffold Height adjustable in 25 cm increments Platform height max 2 00 m Note Follow Instructions for Use Technical Data Permissible...

Страница 99: ...ding Base Unit 160 190 ASW 6 pc 102035 Vertical Frame 70 90 ASW 6 pc 102034 Vertical Frame 70 120 ASW 2 pc 102026 Entry Platform 190 ASW 1 pc 102030 Toe Board Set 70 190 ASW 4 pc 102027 Double Guardra...

Страница 100: ...SD 75 Note Follow Instructions for Use Technical Data Permissible load bearing capacity 150 kg 1995 1030 100 1038 2115 750 1150 118331 118323 13 500 18 000 Handrail Units SD Handrail Unit SD 75 Handra...

Страница 101: ...5 145 118622 4 870 Transition Prophead SDSK For the rectangular change of the direction of the Main Beam SLT in the standard application with Prophead SSK 266 129 250 126580 134 000 Pallet Handrail Un...

Страница 102: ...trasse 19 89264 Weissenhorn Germany Tel 49 0 7309 950 0 Fax 49 0 7309 951 0 info peri com www peri com System Independent Accessories Column Formwork Wall Formwork Slab Formwork Climbing Systems Bridg...