18.2
Control Units in a TLON network
The EBL512 G3 system can be build up as a single TLON Network or
as a redundant TLON Network, i.e. two networks.
In the
single TLON Network
, one TLON connection board (1590)
has to be plugged in each control unit (Network no. 0) whereas in the
redundant TLON Network
, two connection boards (1590) have to
be plugged in each control unit.
The redundant TLON Network supports full functionality also in case
of a network fault, i.e. open circuit or short circuit in one of the TLON
networks.
Network no. 0
When the 1590 board is on place and the network cables are
connected
35
,
for each control unit
, do as for a single control unit, see
1-6 above.
When all control units are powered, the TLON network installation
(see below) has to take place
before
the site specific data (SSD) can
be downloaded, see chapter "Programming (SSD download)", page
75.
If you know that one or more of the control units are to be started-up
later, do as follows:
- In WinG3 create the SSD only for the control units that shall be
connected now. Wait to download the SSD until the TLON Network
installation is ready.
- In TLON Manager, do the TLON Network programming for the
project, i.e. only the control units that shall be connected now.
- When the TLON Network installation – see below – is ready ,
download the SSD.
Later, when one or more control units shall be added to the TLON
Network:
- Open the project in
TLON Manager
, add the control unit(s) and
install (download) it according to the separate TLON network
documentation.
- Open the SSD in WinG3 and add the control unit(s) and download
the SSD to all control units.
18.2.1
TLON network installation
A project (a system with two or more control units) is created in the
PC program
TLON Manager
(or has been created earlier). A PC is
connected to the modular connector "J10" (Network no. 0) in the
35
The TLON connection board is mounted on the main board 5010.
Network cable connections are made on the main board 5010, terminal block
"J4".