950-734-100-01, Revision 01
Installation and Test
PLL-734 List 1
December 18, 1998
7
For further details on the LEDs activities, refer to
“Initialization Sequence” on page 8
and the
“COLU and RT
Fault Indicators” on page 35
.
All alarms in the PG-Plus application are suppressed when initially installed and powered up. Any alarms that are
generated during this process are Suppressed. When the HDSL is synchronized and the COLU and RT margin has
cleared; outstanding alarms that have been Suppressed are made Active and reported to the PAU or the PMU,
based upon their provisioned types.
I
NSTALLATION
AND
T
EST
The following sections describe the tools and procedures for installing and testing the COLU.
R
EQUIRED
T
OOLS
AND
T
EST
E
QUIPMENT
No tools are required to install the COLU. For testing, the following tools may be utilized:
•
Telephone test set
•
Optional, PSU-795 List 1 COTS Continuity Test Card, part number 150-1695-01