Connection Step:
·
Check the grid voltage and compare with the permissible voltage range. (See
technical data).
·
Disconnect the circuit-breaker from all the phases and secure against re-
connection.
·
Trip the wires:
·
Trip all the wires to 52.5mm and the PE wire to 55mm.
Use the crimping pliers to trip 12mm of insulation from all wire ends as below.
Connect AC cables into the “GRID” /”EPS” connectors.
Figure 5-8 Grid cable installation
WARNING!
Make sure you select the correct specification cables for
installation.
Otherwise, the power will make the cable hot or burnt: it could result
in death or serious injury.
Don't connect the phase to 'PE' terminal, otherwise the hybrid
inverter will not function properly.
Содержание BRE-I-5K
Страница 1: ...1 User Manual BRE I 5K OLIPOWER ENERGY AUTOMATION TECHNOLOGY...
Страница 28: ...28 1 ADD Interface ADD interface PINS definition...
Страница 33: ...33...
Страница 34: ...34...
Страница 51: ...51 6 3 5 System Switch Press up or down button to turn on or turn off the inverter Press OK to confirm...
Страница 54: ...54 Reactive power setting After user log into the system Remote control Reactive power...
Страница 55: ...55 Volt watt setting After user log into the system Remote control Australia...
Страница 62: ...62...