Section 75
00-02-0878
2013-03-07
- 100 -
Parameter Settings
In parameter 6006 the switching is made between settings 1 to 4, for the generator,
simply by choosing the desired nominal setting, just as it is for the Busbar group choice
in parameter 6054.
AC Voltage Scaling
Default AC voltage scaling is set to range 100 V-25000 V (parameter 9030). To be able
to handle applications above 25000 V and below 100 V, it is necessary to adjust the
input range so it matches the actual value of the primary voltage transformer. This
makes it possible to support a wide range of voltage and power values.
Setup of the scaling can be done in parameter 9030 from the display window shown in
the following illustration.
Changing the voltage scaling will also influence the nominal power scaling:
Scaling
Parameter 9030
Nom. Settings 1 To 4
(Power) Will Change
According To Parameter
9030
Nom. Settings 1 To 4
(Voltage) Will Change
According To Parameter
9030
Transformer Ratio
Settings
Parameter 6041, 6051
And 6053
10 V-2500 V
1.0-900.0 kW
10.0 V-2500.0 V
10.0 V-2500.0 V
100 V-25000 V
10-20000 kW
100 V-25000 V
100 V-25000 V
1 kV-75 kV
0.10-90.00 MW
1.00 kV-75.00 kV
1.00 kV-75.00 kV
10 kV-160 kV
1.0-900.0 MW
10.0 kV-160.0 kV
10.0 kV-160.0 kV
NOTE:
All nominal values and the Primary Transformer (PT)
settings must be corrected after the scaling has been changed in
parameter 9030.
Содержание EMS-GC10
Страница 1: ...00 02 0878 Section 75 2013 03 07 GensetControllerUnit ModelEMS GC10 Operator sManual ...
Страница 14: ...Section 75 00 02 0878 2013 03 07 8 Menu Structure Diagram ...
Страница 32: ...Section 75 00 02 0878 2013 03 07 26 Mode Shift NOTE To enable mode shift a digital input has to be set up ...
Страница 33: ...Section 75 00 02 0878 2013 03 07 27 MB Open Sequence ...
Страница 34: ...Section 75 00 02 0878 2013 03 07 28 GB Open Sequence ...
Страница 35: ...Section 75 00 02 0878 2013 03 07 29 Stop Sequence ...
Страница 36: ...Section 75 00 02 0878 2013 03 07 30 Start Sequence ...
Страница 37: ...Section 75 00 02 0878 2013 03 07 31 MB Close Sequence ...
Страница 38: ...Section 75 00 02 0878 2013 03 07 32 GB Close Sequence ...
Страница 39: ...Section 75 00 02 0878 2013 03 07 33 Load Takeover LTO ...
Страница 40: ...Section 75 00 02 0878 2013 03 07 34 Island Operation ...
Страница 41: ...Section 75 00 02 0878 2013 03 07 35 Automatic Mains Failure AMF ...
Страница 42: ...Section 75 00 02 0878 2013 03 07 36 Test Sequence ...
Страница 48: ...Section 75 00 02 0878 2013 03 07 42 Stop Sequence The drawings illustrate the stop sequence ...
Страница 74: ...Section 75 00 02 0878 2013 03 07 68 Start ...
Страница 75: ...Section 75 00 02 0878 2013 03 07 69 Stop ...
Страница 183: ...Section 75 00 02 0878 2013 03 07 177 ...