8 Commissioning
Maschinenfabrik Reinhausen GmbH 2022
78
8595028/00 EN
TAPCON
®
250
4. Select the
Measured values
menu item to display the operating values
for current and power and compare them with the values of the operation
measurement instruments.
5. Control the on-load tap-changer manually using the
or
keys
until the measured voltage U
actual
reaches the desired voltage U
desired
("de-
sired value 1").
6. Set the desired value to the value you want.
7. Set the bandwidth depending on the step voltage.
8. Set the delay time T1 to 20 seconds [
9. Set the time response T1 to linear [
10. Press
to raise the on-load tap-changer one step.
11. Press
to select auto mode.
ð
If the actual voltage is outside the bandwidth, the device returns the
on-load tap-changer to the original operating position after 20 sec-
onds.
12. Press
to select manual mode.
13. Press
to lower the on-load tap-changer one step.
14. Press
to select auto mode.
ð
If the actual voltage is outside the bandwidth, the device returns the
on-load tap-changer to the original operating position after 20 sec-
onds.
15. Press
to select manual mode.
16. Set the delay time T2 to 10 seconds and activate it [
17. Press
twice to raise the on-load tap-changer two steps.
18. Press
to select auto mode.
ð
If the actual voltage is outside the bandwidth, after 20 seconds the de-
vice lowers the on-load tap-changer one step and after another
10 seconds another step.
19. Press
to select manual mode.
20. Set the delay time T1 [
Page 141] to
the desired value.
We recommend a temporary setting of 100 seconds for
delay time T1
when
commissioning the transformer. Depending on the operating conditions, you
can also specify the delay time following a longer observation period. In this
regard, it is useful to register how the actual voltage progresses and the
number of tap-change operations per day.