50
SyncServer 600 Series User’s Guide
098-00720-000 Revision B – April, 2016
Chapter 2 Installing
Installation Check List
Figure 2-16. Alarm Connections
Installation Check List
To verify that the installation of the SyncServer S6x0 is complete, perform the
checks and procedures in
.
Applying Power to the SyncServer S6x0
The SyncServer S6x0 is not equipped with a Power switch. After installing the unit
in a rack and making the necessary connections described in previous sections,
turn on power at the distribution panel.
Normal Power Up Indications
As the SyncServer S6x0 powers up and begins normal operation, the LEDs all turn
on. After the self-test is complete and the firmware is operational, the LED states
may change to indicate the appropriate state or status.
provides a description of the SyncServer S6x0 LEDs.
Table 2-4. Installation Completeness Checklist
Operation
Complete
Ensure the SyncServer S6x0 chassis is securely attached to mounting rack
Verify that all power and ground wires are installed correctly and securely
Verify that all communications cables are properly installed
Verify that all input and output cables are properly installed
Table 2-5. LED Descriptions
Label
LED
Description
SYNC
Clock Status
Green
- Time or Frequency clock in Normal or
Bridging state
Amber
- Time or Frequency clock in Freerun or
Holdover state