IOMM AGZ-3
AGZ 035A through 065A
53
Interlock wiring
The installing contractor provides all interlock wiring to field devices (such as flow switches and
pump starters). See unit wiring diagrams and field wiring diagram.
Unit set points and calibration
The control software is installed and tested by the factory before shipping. Calibration of the
controller is not necessary. All control and equipment protection set points must be checked by the
installing contractor and adjusted as necessary before starting the unit. Controllers for McQuay
chillers have default set points. Refer to the menu items listed below.
•
Control mode
•
Leaving water temperature
•
Head pressure settings
•
Compressor staging
•
Soft loading
•
Holiday dates
•
Internal scheduling
•
Alarm functions
The default settings are suitable for most installations. The control mode is factory set for “Manual
Unit Off”. Check and set the control and equipment protection settings for the application before
starting the unit. For more information on menu items, see the menu description section.
Modem kit
An optional modem kit allowing remote monitoring of the chiller from an off-site PC running
McQuay Monitor software is available from your local McQuay International sales representative.
The modem kit comes complete with modem, mounting bracket, wiring harness, and installation
instructions. The modem kit can be field installed or as an option at the factory. Modem wiring is
shown on the field wiring diagram.
Lead-Lag
A feature on all McQuay AGZ air-cooled chillers is a system for alternating the sequence in which the
compressors start to balance the number of starts and run hours. Lead-Lag of the refrigerant circuits
is accomplished automatically through the MicroTech Controller. When in the auto mode the circuit
with the fewest number of starts will be started first. If all circuits are operating and a stage down in
the number of operating compressors is required, the circuit with the most operating hours will cycle
off first. The operator can override the MicroTech controller, and manually select the lead circuit as
circuit #1, #2, #3 or circuit #4.
Содержание AGZ 035A
Страница 6: ...6 AGZ 035A through 065A IOMM AGZ 3 Figure 3 Clearance Requirements...
Страница 18: ...18 AGZ 035A through 065A IOMM AGZ 3 Electrical Legend Figure 8 Electrical Legend...
Страница 19: ...IOMM AGZ 3 AGZ 035A through 065A 19 Figure 9 Typical Field Wiring with Global UNT Controller...
Страница 20: ...20 AGZ 035A through 065A IOMM AGZ 3 Figure 10 Typical Field Wiring Diagram with MicroTech Controller...
Страница 21: ...IOMM AGZ 3 AGZ 035A through 065A 21 Figure 11 Single point Connection with FanTrol...
Страница 22: ...22 AGZ 035A through 065A IOMM AGZ 3 Figure 12 Single point Connection with SpeedTrol...
Страница 23: ...IOMM AGZ 3 AGZ 035A through 065A 23 Figure 13 Unit Control Schematic UNT...
Страница 24: ...24 AGZ 035A through 065A IOMM AGZ 3 Figure 14 Staging Schematic UNT...
Страница 25: ...IOMM AGZ 3 AGZ 035A through 065A 25 Figure 15 MicroTech Controller Schematic...
Страница 26: ...26 AGZ 035A through 065A IOMM AGZ 3 Figure 16 Unit Control Schematic MicroTech...
Страница 27: ...IOMM AGZ 3 AGZ 035A through 065A 27 Figure 17 Staging Schematic MicroTech...
Страница 94: ...94 AGZ 035A through 065A IOMM AGZ 3 Notes...
Страница 95: ......