Unit Set Points and Calibration
The control software is installed and tested by the factory before shipping. No periodic calibration of
the controller is necessary. All control and equipment protection set points must be checked by the
installing contractor and adjusted as necessary before starting the unit.
The “setpoint” control knob adjusts the leaving water setpoint. The “Control Band” knob adjusts the
controller temperature control band. To set, divide the chilled water temperature range by the number
of unloading steps and add 0.5°F.
Optional Sensors
Optional sensor kits, available from the factory, can be installed in the field. The optional sensor kits
have the same characteristics as the leaving water sensor.
Field Wiring
Interconnecting wiring for the control panel may consist of the following:
•
115Vac power wiring
•
Analog input signals
•
Digital input signals
•
Digital output signals
•
Communications to a personal computer
Power Wiring
The installing contractor provides the unit voltage power source, disconnect, fuses and necessary
wiring for these circuits. All wiring must conform to the National Electrical Code and applicable
local building codes. If the evaporator heater power source (120Vac) is supplied from a separate
external supply, remove wires 540 and 545 as indicated on the unit wiring diagram.
Power Supplies
There are several internal power supplies used by the controller and related circuitry. The regulated
5Vdc power is supplied by RSP1 and provides power to pressure transducers. Do not use this power
supply to operate external devices. A 24Vac power supply is available for the alarm bell option. Wire
according to the unit wiring diagram.
Analog input signals
All sensors and transducers required for normal chiller operation are installed and wired at the factory.
All optional analog input signal wiring is provided by the installing contractor must be twisted,
shielded pair (Belden #8760 or equal). The optional demand limit and remote reset signals are 0 to
10Vdc signals. The controlling range of the remote reset signal is from 2Vdc to 10Vdc.
Digital input signals
Remote contacts for all digital inputs into the Global UNT controller must be dry contacts suitable for
the 24Vac control signals from the control panel. Do not connect 120Vac power to the digital inputs
or 24Vac from an external power source.
Remote Stop/Start
If remote stop/start control is selected, remove the jumper between terminals #140 and #141 on TB-7
and install the input between these terminals. When the remote stop/start switch is open, the
controller will be in the unoccupied mode.
Содержание AGZ 035A
Страница 6: ...6 AGZ 035A through 065A IOMM AGZ 3 Figure 3 Clearance Requirements...
Страница 18: ...18 AGZ 035A through 065A IOMM AGZ 3 Electrical Legend Figure 8 Electrical Legend...
Страница 19: ...IOMM AGZ 3 AGZ 035A through 065A 19 Figure 9 Typical Field Wiring with Global UNT Controller...
Страница 20: ...20 AGZ 035A through 065A IOMM AGZ 3 Figure 10 Typical Field Wiring Diagram with MicroTech Controller...
Страница 21: ...IOMM AGZ 3 AGZ 035A through 065A 21 Figure 11 Single point Connection with FanTrol...
Страница 22: ...22 AGZ 035A through 065A IOMM AGZ 3 Figure 12 Single point Connection with SpeedTrol...
Страница 23: ...IOMM AGZ 3 AGZ 035A through 065A 23 Figure 13 Unit Control Schematic UNT...
Страница 24: ...24 AGZ 035A through 065A IOMM AGZ 3 Figure 14 Staging Schematic UNT...
Страница 25: ...IOMM AGZ 3 AGZ 035A through 065A 25 Figure 15 MicroTech Controller Schematic...
Страница 26: ...26 AGZ 035A through 065A IOMM AGZ 3 Figure 16 Unit Control Schematic MicroTech...
Страница 27: ...IOMM AGZ 3 AGZ 035A through 065A 27 Figure 17 Staging Schematic MicroTech...
Страница 94: ...94 AGZ 035A through 065A IOMM AGZ 3 Notes...
Страница 95: ......