Retracting and Locking a Telescopic Section
During telescoping motion you are not to select Lock. Under
no circumstances, while the tele cylinder is moving, should
you select and press the symbol (4, Figure 4-129).
•
Retract the telescopic section slowly and as far as
possible, refer to Table 4-1 for the expected value for the
precision length sensor (Item 2 in Figure 4-128) when
the boom sections are fully retracted.
•
Now select and confirm the symbol (1, Figure 4-129).
The telescopic section can be locked (if the actuator is able
to release the section pins, and the telescoping boom
section is actually aligned with a pinning hole). The screen
should appear as shown in Figure 4-132. In particular,
S2111N should be ON.
FIGURE 4-132
8854-259a
1
CAUTION
Machine Damage Hazard!
If you select Lock during telescoping, the locking pins on
the telescopic section are slid out immediately and they
can damage or tear the electrical or hydraulic components
in the main boom.
Table 4-1 Locking point distances for telescopic boom sections (Millimeter)
T1 (mm)
T2 (mm)
T3 (mm)
T4 (mm)
T5 (mm)
T6 (mm)
0%
0
269
531
794
1057
1277
50%
4140
4444
4699
4923
5063
5172
92%
7591
7927
8174
8366
8403
8418
100%
8249
8590
8836
9022
9039
9036
Table 4-2 Locking point distances for telescopic boom sections (Feet)
T1 (ft)
T2 (ft)
T3 (ft)
T4 (ft)
T5 (ft)
T6 (ft)
0%
0.00
0.88
1.74
2.60
3.47
4.19
50%
13.58
14.58
15.42
16.15
16.61
16.97
92%
24.90
26.01
26.82
27.45
27.57
27.62
100%
27.06
28.18
28.99
29.60
29.66
29.65
Содержание Grove GRT8120
Страница 1: ...Operator Manual Grove GRT8120 ...
Страница 4: ...THIS PAGE BLANK ...
Страница 16: ...TABLE OF CONTENTS GRT8120 A 12 THIS PAGE BLANK ...
Страница 24: ...INTRODUCTION GRT8120 OPERATOR MANUAL 1 8 Published 3 22 2021 Control 702 02 THIS PAGE BLANK ...
Страница 74: ...SAFETY INFORMATION GRT8120 OPERATOR MANUAL 2 50 Published 3 22 2021 Control 702 02 THIS PAGE BLANK ...
Страница 182: ...OPERATING PROCEDURES GRT8120 OPERATOR MANUAL 4 52 Published 3 22 2021 Control 702 02 FIGURE 4 54 ...
Страница 184: ...OPERATING PROCEDURES GRT8120 OPERATOR MANUAL 4 54 Published 3 22 2021 Control 702 02 FIGURE 4 55 1a 1b 1c 1d 1e 1f ...
Страница 186: ...OPERATING PROCEDURES GRT8120 OPERATOR MANUAL 4 56 Published 3 22 2021 Control 702 02 FIGURE 4 56 1a 1b 1c 1d 1e 1f 1g ...
Страница 188: ...OPERATING PROCEDURES GRT8120 OPERATOR MANUAL 4 58 Published 3 22 2021 Control 702 02 FIGURE 4 57 ...
Страница 190: ...OPERATING PROCEDURES GRT8120 OPERATOR MANUAL 4 60 Published 3 22 2021 Control 702 02 FIGURE 4 58 ...
Страница 221: ...Grove Published 3 22 2021 Control 702 02 4 91 GRT8120 OPERATOR MANUAL OPERATING PROCEDURES 4 THIS PAGE BLANK ...
Страница 378: ...5 70 Published 3 22 2021 Control 702 02 SET UP AND INSTALLATION GRT8120 OPERATOR MANUAL THIS PAGE BLANK ...
Страница 440: ...GRT8120 OPERATOR MANUAL A 10 Published 3 22 2021 Control 702 02 THIS PAGE BLANK ...
Страница 447: ......
Страница 448: ......