Lucent Technologies 415B Battery Plant for 4ESS
Issue 6 September 1999
System Testing 5 - 1
5
System Testing
Test Equipment
Required
The following equipment is required to test the 415B Battery
Plant:
•
300 watt test load – 2 amperes @ 150 volts
•
90 kilowatt load box – 600 amperes @ 150 volts
[(3) ITE – 5317 load boxes may be used]
•
DMM (digital multimeter) with 4-1/2 digit display and
0.05% accuracy or better
•
Calibrated clamp-on DC current meter (0.1 ADC
sensitivity)
•
Battery Plant Simulator Test Set (ITE-7102)
•
Standard installation tools, screwdrivers, etc.
•
J87132B-2 Rectifier product manual
•
Galaxy Controller for 415B Battery Plant product manual
•
Rubber gloves
•
Windows-based personal computer (PC) with EasyView
software installed
•
Cable to connect PC communication port to local port of the
controller
Power Up of
415B Battery
Plant
1. Perform the following verification checklist:
– The frames of all cabinets are properly grounded.
– The ground from return to CO Ground through the
Enhanced Ground Current Monitor is installed correctly.