Lucent Technologies 415B Battery Plant for 4ESS
7 - 34 Retrofit of 415A Battery Plant
Issue 6 September 1999
Bolting Hardware
The Control and Distribution Bay contains the bolting hardware
for mounting both the ac cabinet and Control and Distribution
Bay to the floor. Figure 7-14 shows a typical floor mounting
detail. Figure 7-15 is a floor-mounting template.
Figure 7-14: Typical Floor Mounting Detail
Figure 7-15: Floor Mounting Template for Control
and Distribution Bay
HOLD DOWN PLATE
(2 PLACES)
FRAMEWORK
BASE
FLOOR ANCHOR BOLT
(HILTI) (4 PLACES)
HOLD DOWN WASHER
(4PLACES)
FLOOR COVERING
18mm diameter x 100mm deep
(0.75 inch diameter x 4 inch deep
allowed as substitute)
2.38
12
7.25
2
3.25
2.5
2
21
26
2
1
1
2
2
3
3
4
4
3
3
4
4
1
1
2
2
H569-429
Base
Concrete edge to hole center distance to be at least 2.5 inches.
Drill 4 holes, position 1. If interference in reinforced concrete occurs,
use position 2, 3, or 4 in that order.
2
1