Retrofit of 415A Battery Plant 7 - 57
9. Repeat this procedure for each rectifier.
MAN Leads
This test is done with the battery connected to the Control and
Distribution Bay, 10 - 20 amperes load, and all rectifiers on.
1. Turn off one of the rectifiers.
2. Verify that MIN and RECT alarms are displayed on the
Galaxy and that a PMN is remoted.
3. Turn the rectifier on; the alarm should clear.
4. Repeat Steps 1 through 3 for all rectifiers.
VI and VP Leads
Refer to Section 7, Glossary, for the definitions of VI and VP.
1. Before adjusting the VI signal, locate the BJB board inside
the Galaxy controller.
2. Verify that SW202 position #8 is at the “1” or “closed”
position.
3. Configure the controller for rectifiers. You can configure
the rectifiers from the front panel of the Galaxy by doing
the following:
Press MENU
→
CONFIG
→
RECT
DEF
Press ENTER; the display will now show:
RECT DEF
G01 (flashing)
Note: G01 represents rectifier one and you will see it
flashing off and on.
Press ENTER; the display will now show
RECT 01
TYPE: UNCONFIGURED (flashing)
SHUNT mV: 50.00
MAN SW: NONE
Press or - to scroll through menu until
J87132B-2 appears in TYPE: