Open all isolation valves that may have been installed in the piping system. Water source unit service valves must remain closed.
Perform a Pressure (Leak) Test
Use medical grade dry nitrogen, and pressure test the refrigerant piping system using a multi step process that will assist in locating leaks (if
any).
1. Pressure test the main piping only using field installed Schrader valves and pressure gauges. If the test is successful the main lines do
not have leaks.
•
150 psi for a period of 5 minutes
•
300 psi for a period of 15 minutes
•
550 psi for a period of 24 hours
2. Next pressure test the piping up to and including the indoor units. If the test is successful the run-out pipes and indoor units do not have
leaks.
•
150 psi for a period of 5 minutes
•
300 psi for a period of 15 minutes
•
550 psi for a period of 24 hours