4-18
RISK ASSESSMENT
Both prior to and during the installation of an Kidde IGS, there are a number of aspects to
consider in order to have a safe working place and to enable the safe handling of the equipment
to be installed.
Below is listed a number of risks that have to be considered and addressed.
Table 4-16. Risk Assessment Table
Item
Hazard
A.
Health and Safety
A.1
Cylinder Handling, no transport cap fitted,
non secured cylinder
Cylinder can fall/tip, breaking off the valve
personnel can get severely hurt
A.2
Improper cylinder trolley
Cylinder may “fall” off breaking off the valve,
personnel can get severely hurt
A.3
Welding activities.
Fire can occur, welding can pollute the air
A.4
Dust from drilling
Breathing problems, dust in eyes
A.5
Sloppy operation with extension cores for
electrical tools, lighting.
Fitter can stumble and get hurt
A.6
Messy area at cutting and threading.
Fitter can stumble and get hurt
A.7
Cylinder assembly used as scaffolding
Manifold can, break loose and damage the
cylinder valves
A.8
Other mechanical work in progress during
cylinder assembly
Scissor lift, fork lift truck can tumble the
cylinders, breaking off the valve personnel
can get severely hurt
B.
Technical
B.1
Proper installation
Failure of installed equipment with possible
replacement issues as a result
B.2
Damaging of installed equipment
Damages due to substandard workmanship
or other activities after installation,
necessitating replacement.
B.3
Welding
Welding not performed correctly resulting in
need for difficult repair works
B.4
Equipment too heavy
Concrete floor will break/be damaged
necessitating repair (civil works and/or
equipment).
B.5
Equipment too large in size
Installation cannot be performed due to new
design/equipment to be provided
B.6
Cores in cables to solenoid valves too small
Power supply to solenoid valves may be
reduced to the point where it may be
insufficient to open the valve.
C.
Interfaces
C.1
Access to area for installation of each
system
Owner delayed with civil works causing
delay to whole project time schedule
C.2
Technical interface with fire detection &
control system
Extinguishing System does not have proper
function due to lack of electrical input.
C.3
Materials not on Site before installation start Installation cannot start as planned
Содержание 400 Series
Страница 2: ...Table i Revision History Revision Change Description AA Initial Release ...
Страница 16: ...July 2018 xiv 06 237518 001 THIS PAGE INTENTIONALLY LEFT BLANK ...
Страница 157: ...06 237518 001 A 1 July 2018 APPENDIX A SAFETY DATA SHEETS ...
Страница 188: ...July 2018 A 2 06 237518 001 THIS PAGE INTENTIONALLY LEFT BLANK ...
Страница 189: ......